Hi all,
We are not going to provide photos for this credit but we have an IAQ plan developed and the contractor has been following it according to the credit requirement. My question is if we pursue option 2 The Contractor can confirm the implementation of the noted construction and pre-occupancy phase moisture protection methods, should we include all the five SMACNA measures in the narrative? Or it would be enough to just write a description about absorptive materials protection? How detailed should this be?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Michelle Halle Stern
Senior Sustainability ConsultantGreenwood Consulting Group
120 thumbs up
October 26, 2015 - 9:54 am
I would include everything, since all measures are required. Make it detailed enough to understand the measures taken, but short enough that the reviewers can read it quickly.