Ashrae 90.1 2010 Appendix G

NC-v4 EAp2:Minimum energy performance
posted by  junaid naseer  on 

Do we need to follow addendums of ASHRAE 90.1 2010 in relation to Appendix G for compliance? For instance, addendum F restricts window to wall ratio to 34% for hotel/motel with rooms greater than

1
Mon Apr 25, 2016, 2:18 pm

Exterior lighting for group certification

NC-2009 SSc8:Light Pollution Reduction
posted by  Mohamed M. Abd Elhameed  on 

I am currently working on a project with multiple buildings within the LEED boundary. The project will follow group approach registration via campus guidance.

1
Mon Jun 12, 2017, 3:13 pm

Inspection Reports - responsible party

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  komal kotwal  on 

Is it required that the on-site inspection be conducted by a third party or can a Contractor's representative conduct the same?

1
Sun Jan 8, 2017, 5:22 pm
1
Tue Jun 6, 2017, 3:58 pm

Narrative for Option 2 Contractor confimration

NC-2009 IEQc3.1:Construction IAQ Management Plan—During Construction
posted by  Saud Abdul Rasheed  on 

Hi all, We are not going to provide photos for this credit but we have an IAQ plan developed and the contractor has been following it according to the credit requirement.

1
Mon Oct 26, 2015, 1:54 pm

water cooled chilller

NC-2009 EAp2:Minimum Energy Performance
posted by  sherif el adly  on 

Hi Marcus The building size is mandating to model the baseline with a water cooled chiller and I will compare the baseline with the design which is using HVAC that is (air cooled chiller + ice sto

1
Thu Dec 1, 2016, 5:40 pm

modeling with air cooled chiller

NC-2009 EAp2:Minimum Energy Performance
posted by  sherif el adly  on 

the building size is mandating to model the baseline with a water cooled chiller and I will compare the baseline with the design which is using HVAC that is (air cooled chiller + ice storage + dive

0

smoke leakage test for duct

NC-2009 IEQc3.1:Construction IAQ Management Plan—During Construction
posted by  Abdulla Anwar  on 

Our MEP sub-contractor need to clarify if we can use an smoke capsule for duct leakage test, prior to final air leakage test since the project specs is giving a small allowable 1% from basis of des

1
Sat Aug 26, 2017, 8:59 pm

Gypsum board recycling resource, Saudi Arabia

NC-2009 MRc2:Construction Waste Management
posted by  Shreepad Bandagi  on 

Wondering if anyone would have a resource for gypsum board recycling anywhere in Saudi Arabia. Thanks!

1
Wed Jul 9, 2025, 10:09 am

CxA role

NC-2009 EAc3:Enhanced Commissioning
posted by  Abdulla Anwar  on 

Can you advise the CxA role if it was a part of Owner organization? .......................... by the way what is the commissioning developed plan CxP?

1