Required parking lots and LEED boundary Calculations

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  kerry wang  on 

Hi all, We have a question about LEED boundary calculation as below: In order to save the land, our company has set up a shared parking lot in the area, so this project does not have new parking s

0

General Emissions Evaluation

NC-v4 EQc2:Low emitting materials
posted by  Joshua Chia  on 

Hi All! Appreciate if someone can help with the following. The reference guide states that for projects overseas, the products can be tested to either CDPH or AgBB.

1
Mon Nov 27, 2017, 3:29 pm

HVAC System 8 Baseline

CS-2009 EAp2:Minimum Energy Performance
posted by  CINDY CHAI  on 

Hi all, Currently I have a project in Malaysia that is going for LEED Core and Shell (2009), the project consists of multiple buildings but will be certified under one certificate.

3
Default Avatar
ESD SENIOR ENGINEER
KAER SDN BHD
LEEDuser Basic Member
0 thumbs up
Thu Mar 26, 2015, 12:39 am

Mechanical Ventilation using local code

NC-2009 IEQp1:Minimum IAQ Performance
posted by  MOHD HAFIZI MOHAMAD  on 

Hi. Is it a compulsory to design mechanical ventilation by using local code even if ASHRAE Standard is more stringent in order to score IEQ Credit 2: Increased Ventilation? I got a problem to sco

5
Default Avatar
LEEDuser Premium Member
19 thumbs up
Thu Jan 22, 2015, 2:37 am