Water Consumption Outside LEED Boundary
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Aswin M on
We have a garment factory project that has a Main block and two toilet blocks (separately for Men & Women).
Single Building Certification_LEED New Construction 2009
NC-2009 MPR2:Must be a complete, permanent building or spaceposted by Aswin M on
We have a Garment factory project that has three blocks with connectivity bridge. The three blocks are namely Cutting block, Sewing block, and Fabric store block.
Airconditioning for process requirement
NC-2009 EAp2:Minimum Energy Performanceposted by Rathnashree Bharadwaj on
Hi, We are working on a tablet manufacturing facility which is fully air conditioned (Only cooling, no heating requirement).
CO2 SENSOR IN AN UNDERGROUND METRO STATION.
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by VEL MUTHU on
Hello everyone, I am working in a underground metro station which is aiming for LEED certification.
Minimum Ventilation rates for Production area
NC-2009 IEQp1:Minimum IAQ Performanceposted by sriram tetali on
Hi all Can u suggest the Ventilation rates for the Production / manufacturing areas for a Pharmaceutical clients because ASHRAE doesn't mention any for the Production in the Table 6-1
How to prove compliance with Mechanical Ventilation
NC-2009 EAp2:Minimum Energy Performanceposted by Praveenbabu Rajkumar on
The project is a medium sized workshop shed and will be mechanically ventilated with fans with a particular air change per hour as per the local standards.
Basement Ventilation exceptional calculations
NC-2009 EAp2:Minimum Energy Performanceposted by Rathnashree Bharadwaj on
Our project has 4 basements with fresh air, exhaust and circulation fans.
Selection of HVAC Baseline System
NC-2009 EAp2:Minimum Energy Performanceposted by Praveenbabu Rajkumar on
Hi, Sorry for my English Any one can suggest, which is correct baseline HVAC system for following project description. No.