Post a question or comment
Location Filters
Filter by location
Forum
Topic
Replies
Recent

Need Registration guidance for an upcoming Hospital campus

LEED Guidance for Campuses and Multiple Buildings
posted by  Neha Singhal  on 

We have a Medical institution coming up at Faridabad (India), which contains various types of building, where the construction would be carried out simultaneously for all the blocks.

3
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Sun Jan 17, 2016, 4:51 pm

Water Consumption Outside LEED Boundary

NC-2009 WEp1:Water use reduction
posted by  Aswin M  on 

We have a garment factory project that has a Main block and two toilet blocks (separately for Men & Women).

8
Default Avatar
Conserve Consultants Private Limited
LEEDuser Basic Member
5 thumbs up
Mon Jan 4, 2016, 4:52 am

Single Building Certification_LEED New Construction 2009

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Aswin M  on 

We have a Garment factory project that has three blocks with connectivity bridge.  The three blocks are namely Cutting block, Sewing block, and Fabric store block.

7
Default Avatar
Conserve Consultants Private Limited
LEEDuser Basic Member
5 thumbs up
Wed Dec 30, 2015, 5:06 am

Airconditioning for process requirement

NC-2009 EAp2:Minimum energy performance
posted by  Rathnashree Bharadwaj  on 

Hi, We are working on a tablet manufacturing facility which is fully air conditioned (Only cooling, no heating requirement).

3
Tue Nov 3, 2015, 2:21 pm

CO2 SENSOR IN AN UNDERGROUND METRO STATION.

NC-2009 IEQc1:Outdoor air delivery monitoring
posted by  VEL MUTHU  on 

Hello everyone, I am working in a underground metro station which is aiming for LEED certification.

2
Mechanical Engineer
Integral Group
LEEDuser Expert
342 thumbs up
Tue Sep 15, 2015, 2:37 pm

Minimum Ventilation rates for Production area

NC-2009 IEQp1:Minimum indoor air quality performance
posted by  sriram tetali  on 

Hi all Can u suggest the Ventilation rates for the Production / manufacturing areas for a Pharmaceutical clients because ASHRAE doesn't mention any for the Production in the Table 6-1

3
Manager -Sustainability Services
M W Group
LEEDuser Basic Member
1 thumbs up
Fri Mar 27, 2015, 7:01 am

How to prove compliance with Mechanical Ventilation

NC-2009 EAp2:Minimum energy performance
posted by  Praveenbabu Rajkumar  on 

The project is a medium sized workshop shed and will be mechanically ventilated with fans with a particular air change per hour as per the local standards.

8
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Tue Dec 23, 2014, 6:26 am

Basement Ventilation exceptional calculations

NC-2009 EAp2:Minimum energy performance
posted by  Rathnashree Bharadwaj  on 

Our project has 4 basements with fresh air, exhaust and circulation fans.

4
Fri Nov 21, 2014, 2:47 pm

Selection of HVAC Baseline System

NC-2009 EAp2:Minimum energy performance
posted by  Praveenbabu Rajkumar  on 

Hi, Sorry for my English Any one can suggest, which is correct baseline HVAC system for following project description. No.

4
Sun Nov 2, 2014, 11:29 pm