Forum quick links
requirements for secure bicycle storage?
NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Erin Holdenried on
Are racks or bike stands needed? I have a project with a designated area for bicycle storage.
Finishing coating on steel surface
CS-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Indochine Engineering VN on
Hi, my project plans to use 2 coating layers for steel frame structure of façade system, onsite and indoor.
Equation2: Monthly harvested rainwater volume. (v4)
NC-v4 WEc1:Outdoor water use reductionposted by deepak cherukumilli on
Reference guide v4 BD+C:Page290: STEP 5: I didnot understand why a 0.15 is used in this equation. Is this for any kind of losses in the rain water storage process.
n/a
NC-2009 EAc1:Optimize Energy Performanceposted by SAMY Chamy on
Dear Marcus..... Greetings... In one of our project , we have CHP which fall under Case 1 as given in LEED Guide, CHP under Same Ownership..We have 2 nos of 500 KW Gas Generator which supplies
Laundry Chemical
EBOM-v4 EQc7:Green cleaning - products and materialsposted by VISHESH AGARWAL on
Cleaning and Degreasing- CCD-110 is this credit include the laundry cleaning product come under the cleaning and degreasing category.
The overlap activities between CxA and CM Consultant
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Panupant Phapant on
Hi Can anyone share the CxA practice for LEED project in USA or other countries as we see that there are the overlap activities between the construction management consultant and CxA for LEED proje
shop applied adhesive in a laminate flooring
NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Melissa Merryweather on
Our product uses a laminated flooring product. If the laminating adhesive and the finish product are both factory- applied, then do we need VOC tests?
Using Chilled Water Pump similar to ASHRAE 90.1
NC-2009 EAp2:Minimum Energy Performanceposted by Michael Wahjudi on
Hi, we have development where the Chiller Plant is serving three buildings.
Normalizaiton
EBOM-v4 EAp2:Minimum energy performanceposted by Muzammal Abbas LEED AP (BD+C) on
I am working on a industrial project registered in Existing building Operation and maintenance located Out of US , that have its own electricity production of 4 Mw through gas engines and its free
100% irrigation requirement met through treated waste water
NC-2009 WEc1:Water Efficient Landscapingposted by Yusuf Turab on
I find the credit language very confusing.