SRI Value for concerete

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  soha yamani  on 

Is there a standard SRI Value for concrete that i can use to comply with the credit requirements ? as a part of the roof i am using is concerete and the specs is not addressing this part

1
Thu Nov 26, 2015, 10:32 pm

Infill Site

ND-Plan-v4 SLLp1:Smart location
posted by  Jos Schild  on 

Is there a definition of an 'infill site'?

1
Mon Jul 18, 2016, 3:36 pm

LEED NCv 2009 Multi-Family Residential: Apartment

NC-2009 EAp2:Minimum Energy Performance
posted by  junaid naseer  on 

Hi All, I have seen this point tackled in many comments earlier but we still have some doubts. We have a residential building of 16 floors which sits on a podium of 3 floors.

1
Tue Nov 22, 2016, 5:36 pm

Baseline Pumping Power

NC-2009 EAp2:Minimum Energy Performance
posted by  Ahmed Labeeb  on 

Based on ASHRAE 90.1, the chilled water pumping power must be 22 W/gpm and does not mentioned the effect of pumping head.

1
Thu Feb 9, 2017, 1:06 pm

SSp1 and EPA in KSA

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  FABIO VIERO  on 

We are working on two projects located in Saudi Arabia under LEED 2009 certification. We are looking for finding the appropriate measures to be applied, as per EPA’s Construction General Permit an

0
0

Painting or Coating for Steel Structure

CS-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Ali Soufan  on 

Hi In a steel structure building, in which the steel is within the building weather proof, two applications are applied: 1- Fire Proof Paint (applied on site) 2- Solvent Based Top Coat Paint (appli

1
Sun Jan 31, 2016, 3:51 am

green power source

NC-2009 EAc6:Green power
posted by  sherif el adly  on 

The client have a solar park in a land adjacent to the land on which the project will be built.

1
Thu Dec 1, 2016, 7:10 pm

smoke leakage test for duct

NC-2009 IEQc3.1:Construction IAQ Management Plan—During Construction
posted by  Abdulla Anwar  on 

Our MEP sub-contractor need to clarify if we can use an smoke capsule for duct leakage test, prior to final air leakage test since the project specs is giving a small allowable 1% from basis of des

1
Sat Aug 26, 2017, 8:59 pm

Baseline System 2

NC-2009 EAc1:Optimize Energy Performance
posted by  SSN Energy Model  on 

As per Table 6.8.1D, I observed the following EER = 12.3-(0.213*Cap/1000) EER Also, Cap means the rated cooling capacity of the product in Btu/hr.

1
Fri Apr 21, 2017, 2:48 pm