Hi,

The below-mentioned contents were copied from LEED Online form. Could you explain, how the energy star values should be compared with Energy Model?

3
Director
Passive Dynamics Sustainability Consultants
LEEDuser Basic Member
12 thumbs up
Fri Jul 6, 2018, 3:37 pm

Bussiness Transport serving the users of the project.

CS-v4 LTc5:Access to quality transit
posted by  Víctor Ramírez Orozco  on 

We are assessing a project that is in an industrial park far away from the city.

0

MLO Non-Residential Lighting using the Performance Method

NC-v4 SSc6:Light pollution reduction
posted by  Candace Cohen  on 

The MLO says that in order to establish the Total Initial Site Lumens one must use Table D, adding together the Allowed Lumens Per Square Foot and the Allowed Base Lumens Per Site.

2
Sr. Electrical Engineer
Integrated Design Solutions
LEEDuser Expert
516 thumbs up
Tue Jun 26, 2018, 9:23 am

Timeline issues with "Recycle or Reuse Construction and Demolition Waste"

ND-Plan-v4 GIBc16:Solid waste management
posted by  Ilan Yahav  on 

How can we proceed with this credit in a LEED ND-plan, if there is a requirement to track diverted waste?

1
Mon Jun 25, 2018, 3:59 pm
3
Tue Jun 12, 2018, 5:37 pm

Previously developed and graded area by municipality - How long before construction?

NC-2009 SSc1:Site Selection
posted by  Ilan Yahav  on 

I am working on a Non-US project that is located in a new neighborhood that had been graded and developed by the local Municipality (roads and sidewalks) in 2006.

0

Hoarding dimensions

NC-v4 SSp1:Construction activity pollution prevention
posted by  Ahmed Labeeb  on 

Dear All,

Is there any LEED requirement regarding the hoarding dimensions ( distance from ground to the bottom of the panel)?

2
UAE
P&T Architects
LEEDuser Basic Member
1 thumbs up
Thu May 17, 2018, 1:52 am

HVAC Baseline System 8 - with Purchased Chilled Water only

NC-v4 EAp2:Minimum energy performance
posted by  Amgad Khattab  on 

We are working on a project where the selected baseline HVAC system type is 8 with purchased chilled water only from a district cooling plant.

8
Default Avatar
Managing Partner
Engineering Solutions
LEEDuser Basic Member
0 thumbs up
Mon May 14, 2018, 4:30 pm