50% of the "building's" electricity -- for Retail??

Retail-CI-v2009 EAc4:Green power
posted by  Erica Downs  on 

Our CI-Retail project accounts for only about 12% of the overall building.

2
Sat Nov 15, 2014, 12:27 am

Mold Testing Standards

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Susan Walter  on 

We have a project and the owner wants to include testing for mold. We had flooding in a project and two AHUs now show signs of mold.

3
Thu Nov 13, 2014, 9:09 pm

Accused synergies between views documentation & other EQ points

CS-2009 IEQc8.2:Daylight and Views—Views
posted by  emily reese moody  on 

Hello, We received comments back from our Design review that seem illogical to us; we're looking for some opinions/clarifications here. We submitted representative (fabricated) typical, hypotheti

4
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Thu Nov 13, 2014, 5:50 pm

Daylight savings time

Schools-2009 IEQc8.1:Daylight and Views—Daylight
posted by  James Geers  on 

I am assuming the daylight modeling must utilize daylight savings time. Is this correct?

2
Thu Nov 13, 2014, 3:17 pm

EBOM v4 prereqs a barrier?

General forums
posted by  Nadav Malin  on 

Gary--I'm interested in your experience with the College that couldn't do EBOM v4 because of the prereqs. Can you say which prereqs were the challenge?

8
SVP, Marketing, Communications & Advocacy
U.S. Green Building Council
LEEDuser Premium Member
2 thumbs up
Tue Nov 11, 2014, 3:30 pm

Comms/ data room cooling - Process Energy for LEED

NC-2009 EAc1:Optimize Energy Performance
posted by  Victoria Watson  on 

Hi all, I am working on a project where the CRAC unit manufacturers have said they don't need to comply with the efficiency requirements of ASHRAE 90.1 for a data room and comms rooms air conditio

3
Tue Nov 11, 2014, 1:59 pm

LEED v4 delay with ACC implications..??

General forums
posted by  Mark Perepelitza  on 

One thought that keeps coming into my mind is how this comes on the heals of the recently announced 'partnership' with ACC. My guess is that this has something to do with the delay.

6
Environmental Stewardship Manager
Tarkett North America
LEEDuser Basic Member
64 thumbs up
Tue Nov 11, 2014, 1:48 pm

All purpose putty

CS-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  James Emery  on 

I don't believe putty can be categorized as an adhesive or a sealant, but the proposed putty in our project has a VOC of 161 g/l and is being used for filling nail holes and other defects in refurb

3
Principal
Iredale Architecture
LEEDuser Basic Member
0 thumbs up
Tue Nov 11, 2014, 1:23 am

How to model Unit Heaters in Baseline model

NC-2009 EAc1:Optimize Energy Performance
posted by  Dónal O'Connor  on 

To Whom It May Concern: I'm looking for guidance on how unit heaters, radiant panels and electric heaters that are in the proposed design are modeled in the baseline building.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Sat Nov 8, 2014, 10:43 pm

Changing from LEEDv4 to LEED 2009

General forums
posted by  P Fanfulik  on 

I registered a project under LEEDv4 (#100038645) because my anticipated completion was past the LEEDv4 sunset date.

9
Founder & CEO, LEED Fellow, BREEAM Fellow
BuildingWise LLC
LEEDuser Expert
224 thumbs up
Fri Nov 7, 2014, 12:05 pm