We have a new hospital building pursuing LEED-HC that is currently under construction. The hospital just announced a lease with a separate owner that plans on building out a full floor of inpatient / operating suites. This build-out will be 7% of the entire hospital area (the remaining 93% is owner-occupied), will be leased by another entity, will be built by a separate contractor, will be completed at the same time as the main hospital building and does not plan on pursuing LEED-CI. The build-out will make alterations to the building envelope at that floor and may make potential changes to the HVAC system on that floor. We were just prepared to submit design credits for review for the overall project, but our MEP engineer has raised concerns about the energy model. Does this new separate build-out project mean that we must modify the energy model of the overall project to take any envelope and HVAC changes into account?