Using LEEDv4 Fundamental and Enhanced ECx to achieve ID LEED2009

NC-2009 IDc1:Innovation in Design
posted by  Candice Rogers  on 

Hello, This question has 2 parts. 1). Our project would like to submit LEEDV4 Fundamental and Enhanced Cx for Envelope only as ID points in a project registered for LEED 2009.

3
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Tue May 12, 2015, 2:12 pm

What is included in MR Credit 7

EBOM-2009 MRc7:Solid Waste Management—Ongoing Consumables
posted by  cathy keagle  on 

In our latest review we were told that landscape waste is not to be included in the calculations for this credit. This appears to be inconsistent with your opening guidelines.

6
Thu May 7, 2015, 9:14 pm

Drain Water Heat Recovery System

NC-2009 EAp2:Minimum Energy Performance
posted by  Luis Barros  on 

A client wants to utilize our Zypho Drain Water Heat recovery system for a hospitality project. The client wants to confirm the availability of LEED credits.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon May 4, 2015, 1:41 pm

Enter way/Filling out the Form

CI-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Bridgett Weaver  on 

Working on a project that the occupancy of the building is a multi-tenant.

4
Thu Apr 30, 2015, 2:50 pm

Frit on Glazing for LEED-2009

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Sara Zoumbaris  on 

Hello, I posted this question on an older thread but will start a new discussion here.

2
Sustainable Design Consulting
LEEDuser Basic Member
20 thumbs up
Wed Apr 29, 2015, 1:47 pm

Are exceptions mandatory or optional?

NC-2009 EAc1:Optimize Energy Performance
posted by  John Krutko  on 

Under ASHRAE 90.1 - G3.1.1 do I HAVE to use exception C for any zones having special pressurization relationships, cross contamination requirements, or code-required minimum circulation rates?

3
Default Avatar
Sr Project Manager
Osborn Engineering
LEEDuser Basic Member
1 thumbs up
Wed Apr 29, 2015, 1:23 pm

The vent calcs indicate a total area significantly lessthan Plf2

NC-2009 IEQp1:Minimum IAQ Performance
posted by  Matt Dem  on 

Hi, Can please someone give his/her suggestion on the question I have below ? I received a comment for (Design Preliminary Submission) ventilation calculations indicate a total area (3,055 sqf)

5
Sr. Sustainability Consultant
Taitem Engineering
LEEDuser Basic Member
36 thumbs up
Tue Apr 28, 2015, 4:05 pm

Dining Halls

NC-2009 EAc4:Enhanced Refrigerant Management
posted by  Laura Charlier  on 

Does anyone have any experience earning compliance with this credit in a Dining Hall application?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Apr 28, 2015, 3:24 pm

VOC content for Shop applied finishes

NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by   Jeremy Mendenhall  on 

We are new to the Leed program and wanting to make sure that we are following all of the guidelines, we have received some instruction however I'm trying to get confirmation that shop applied fini

4
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Mon Apr 27, 2015, 10:37 pm

Floor Coating that Exceeds VOC Limit

CS-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Amanda Atkinson  on 

We have two CS v2009 projects in which a single epoxy floor coating exceeds the allowed VOC content. All other flooring products and coatings are compliant.

2
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Mon Apr 27, 2015, 8:32 pm