Cx - Warranty Review After Building is Sold
NC-2009 EAc3:Enhanced Commissioningposted by Andy Smith on
We completed fundamental and enhanced Cx for a building in August of 2016 (with the exception of 10 month warranty review).
Integrative Pilot Credit - Design or Construction Credit
Pilot-Credits PC60:Integrative Processposted by Devki Wright on
Hi there - when submitting the documentation for this credit, is this considered a design or construction credit?
LEED Schools or LEED CI?
Schools-NC-v4 MPR2:Must use reasonable LEED boundariesposted by Peter Doo on
We are pursuing an interior renovation of a k-12 school building to ongoing school use. Can we use LEED CI or must we use LEED Schools?
Existing Building Baseline Inquiry
NC-2009 EAc1:Optimize Energy Performanceposted by Scott Glancy on
The project consists of upgrading a liquid helium (LHe) to gaseous helium (GHe) conversion and compression system.
Low Mercury Credit - Cafeteria Kitchen Equipment
EBOM-2009 MRc4:Sustainable Purchasing—Reduced Mercury in Lampsposted by Sara Zoumbaris on
Hello, Although I am pursuing this credit as ID for LEED-CI, I am posting this question here.
Non-Conventional purchases
EBOM-v4 MRc1:Purchasing - ongoingposted by Becky Stumm on
I'm working on a convention center, and they don't buy many office supplies. Their major purchases are cleaning supplies ( and fits in the IEQ- green cleaning credit) and uniforms.
Classification of handsinks
CS-2009 WEc1:Water Efficient Landscapingposted by Sean Blaevoet on
How are "handsinks" classified? Is it lavatory? Is it kitchen sink? Or is it exempt? Or other?
ASHRAE 62.1
NC-2009 IEQp1:Minimum IAQ Performanceposted by Kristopher Lashley on
We have an electrical room on site that is not attached to the main building and will hold the electrical equipment for a diesel fueling station.
Building Envelope Seasonal Testing & General Comment
CS-v4 EAc1:Enhanced commissioningposted by Brian Salazar on
Hi! In general, the guidelines for this credit are...very general and vague.
Major Renovation vs. New Construction
NC-v4 EAc2:Optimize energy performanceposted by Eric Webber on
We are in the conceptual design phase of a project consisting of renovations to an existing building and a significant addition.