Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Punit Jain on
I am working on a LEED certification for a new building that is attached via a small circulation bridge to an existing LEED-Certified building on a college campus.
Vista Users Out of Luck
posted by Cynthia Kaplan on
On 9/26/14 I lost the ability to view credit tempolate forms in LOL v3. Three weeks and 163 phone minutes later, the final verdict from GBCI is to buy a new computer.
Example narrative using local standards and codes
Schools-2009 SSp1:Construction Activity Pollution Preventionposted by Dennis Palmer on
Does anyone have a sample of the verbage they have used for the SSp1 Prereq using local standards and codes?
EAp2 Domestic Hot Water Pump sizing
NC-2009 EAp2:Minimum Energy Performanceposted by MKK LEED on
Hello, Appendix G Table G.3.1 - Service Hot water systems states "The service hot-water system in the baseline building design shall use the same energy source as the corresponding system in
LEED EQ 4.2 Wallpaper Compliance
posted by Saahiti Penigalapati on
One of the credits we are attempting on a LEED project is the EQ 4.2 (Low Emitting Materials-Paints and coatings).
RE: Vanpool Parking for a Core and Shell
CS-2009 SSc4.4:Alternative Transportation—Parking Capacityposted by Troy Glasner on
Hello, I am working on a C&S project. The minimum parking capacity set by local zoning is 165 parking spots. The project has 165 spots exactly. The project size is 86000 sq ft.
Campus Registration instead of Block?
posted by Deborah Lucking on
Hello all. I notice on LEED Online that there is now an option to register a new project under "Campus" but not under "Block", which USED to be the way to start the registration process for multipl
Cafeterias with kiosks,
NC-2009 IEQc6.1:Controllability of Systems—Lightingposted by Aishwarya Balagopal on
We are currently working on a cafeteria project for a campus project. The cafeteria has several food serving kiosks (zones) distributed across the dining floor plan.
Limited access for inpatient units
Healthcare-v2009 SSc9.2:Connection to the natural world - direct exterior access for patientsposted by Brian Pescod on
We're looking at this credit as a potential Innovation in Design for a Long-Term Care BD+C project.
Critical Path Supply Duct Pressure Drop Calculations
CI-2009 EAc1.3:Optimize Energy Performance—HVACposted by Bryan Lanier on
Currently working on a tenant project. Base building chilled water to each floor supplying DOAS Terminal Units. I'm planning on supplying PD calcs for representative units.