Thermal zones split and AHU serving them
CS-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings,
Exterior Lighting power - Non-tradable - Facades
CS-v4 EAp2:Minimum energy performanceposted by Vassil Vassilev on
Greetings,
There is a question about the non-tradable surfaces of the exterior lighting, specifically Facades lighting.
Is there a minimum period required for joint-use
Schools-2009 SSc10:Joint Use of Facilitiesposted by Ward Miller on
The school is not in session for 16 weeks of the year and the entire campus and all facilities are with little to no use. Only several security, cleaning staff and administrators are pres
EPD Language
CS-v4 MRc2:Building product disclosure and optimization - environmental product declarationsposted by Ward Miller on
Our project will be supplied bricks from Austria and potentially rebar from Turkey or Bosnia and Herzegovina.
Baseline Fan Adjustment
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, There is an issue I'd like to ask some advice about it. It is for Baseline fan adjustment.
Equipment as per table 6.8.1.A 90.1-2007
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, In the project we are modeling, there are air conditioners which are supposed to operate in cooling mode at OA temperature close to the design heating OA. In this table and also in othe
Baseline Chilled water pumps - G3.1.3.10
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, The standard states that the pump power must be 22 W/gpm. If the project has two chillers and primary secondary circuits, whereby there is on pump per chiller in the primary circuits and
Table 6.8.1 for air cooled liquid chillers
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, In the project we are modeling, on the plant level there are selected Air cooled chilled water chillers, which are also arranged to operate as Heat Pump water heating package (using the
Entering nonregularrly occuoied spaces in IEQp1 calculator
NC-v4 EAp2:Minimum energy performanceposted by Vassil Vassilev on
Greetings, In the IEQp1 calculation form, provided by USGBC for using in LEED v4, in the Occupancy Category pull-down menu, there is nothing related to equipment rooms, non-occupied stores and sim
Automatic metered urinals
CS-2009 WEp1:Water Use Reductionposted by Ward Miller on
Metered showers and faucets appear to be rather clear based on the available LEED information and the new Water Use Reduction Calculator, but metered urinals appear to be overlooked.