FAHU's Fan power and Cooling capacities
CS-2009 EAc1:Optimize Energy Performanceposted by Manivel Natarajan on
Hi All, In my project, proposed building has DX split unit HVAC System.
Natural Ventilation Loads Modeling
NC-2009 EAp2:Minimum Energy Performanceposted by Sefa Sahin on
Dear All, We are working on residential building in Istanbul/Turkey. The building is heated and cooled by radiators and split AC respectively.
Between LEED v4 BD+C:NC or LEED v4 ID+C: CI
posted by Edgar Arevalo on
This may be a silly question, but I ask in order for some clarification. I have a particular question using the 40/60 rule.
LEED v2009 CS+ID Point
CS-2009 IDc1:Innovation in Designposted by Britt Valdez on
In seeking IDc1 Innovation and Design point for LEED CS v2009, would the purchase of carbon offsets to reduce natural gas emissions be acceptable in achieving the ID point?
Distric Energy System
NC-2009 EAp2:Minimum Energy Performanceposted by Gina Dederer on
Dear all, Currently we are working on an industrial facility pursuing LEED 2009 NC – Major Renovation certification. The building consists of 3 levels.
"Exempted" option gone from v5.0 Form
NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Erica Downs on
On version 4.0 of the LEED Online Form, if you selected "Flooring: Mineral-based" or "Unfinished/Untreated Solid Wood", then under "Referenced Standard" the word "exempt would appear.
Critical Path Supply Duct Pressure Drop Calculations
CI-2009 EAc1.3:Optimize Energy Performance—HVACposted by Bryan Lanier on
Currently working on a tenant project. Base building chilled water to each floor supplying DOAS Terminal Units. I'm planning on supplying PD calcs for representative units.
What percentage of products purchased count towards the credit.
EBOM-v4 EQc7:Green cleaning - products and materialsposted by Janet Salisbury on
There is some confusion regarding on what percentage of "green" cleaning products are required to get a point. Is it 30% or 75%. Was this something changed in the new version 4?
Existing Building, Renovations Taking Place Piecemeal
CI-v4 EQc4:Indoor air quality assessmentposted by Sara Zoumbaris on
We have a university lab project that is renovating a select number of rooms, with varying materials/ systems being replaced at different times.
Number of cycles
EBOM-v4 WEc3:Cooling tower water useposted by Jonathan Miller on
What is the number of cycles necessary to achieve 1 point? 10?