EBOM-v4 EQp1:Minimum indoor air quality performanceposted by Gustavo De las Heras Izquierdo on
Hallo, I am reading Section 6.2.7 ASHRAE 62.1-2010, and it is not clear to me if the building needs to install DCV.
n/a
NC-2009 IEQp1:Minimum IAQ Performanceposted by Anastasia Makarenko on
Our project is a big confectionary plant situated in Russia.
ieqc8.1 x ieqc 8.2
NC-2009 IEQc8.2:Daylight and Views—Viewsposted by GISELA FARHAT DE ARAUJO on
to achieve this credit we must have won the ieqc8.1 credit? or credits are independent?
water bills received every 3 months
EBOM-2009 EAp2:Minimum Energy Efficiency Performanceposted by Agnieszka Rylska on
Our project receives water bills including water usage every 3 months.
BAS
EBOM-2009 EAc3.1:Performance Measurement—Building Automation Systemposted by VISHESH AGARWAL on
Is it necessary to have exterior lighting monitor and control to achieve this credit point. if interior is on BMS, Will i able to take that credit.
LEED Dynamic Plaque vs EB Recertification
posted by Michael Chermak on
I'm not seeing much information in these LEEDuser forums on the LEED Dynamic Plaque (since 2014) as compared to recertification (since 2012).
Pilot Credit 101
Pilot-Credits EQpc78:Design for active occupantsposted by Kiyomi Kurooka on
This was the first time our office participated in a Pilot Credit.
CI - applicable when the tennant is the owner?
CI-2009 MPR1:Must comply with environmental lawsposted by Tom Kennedy on
The language of The Reference Guide and MPR's don't seem to quite come out and make this clear; so I figured I would just ask - - suppose a company owns a building, lives and works in that buildin
Energy model OA report
NC-2009 EAp2:Minimum Energy Performanceposted by Jatuwat Varodompun on
If a zone has a large exhaust fan which the exhaust rate is greater than the OA intake at the AHU (the rest of OA will be transferred from other zones , make up air, or infiltration).
Kitchen Energy Model
NC-2009 EAp2:Minimum Energy Performanceposted by Jatuwat Varodompun on
In the normal case for baseline system 5-8, does a kitchen must be modeled as a separated HVAC system using system 3-4.