EAp2 Form

CS-2009 EAp2:Minimum Energy Performance
posted by  Lily Li  on 

in EAp2 Form Summary shows "N", but no error information provided, is this Form wrong?

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Sep 5, 2014, 8:51 pm

Discrepancy in graywater volume between Engineer & ELED

NC-2009 WEp1:Water Use Reduction—20% Reduction
posted by  Maya Karkour  on 

Dear all, We are consulting for a big retail shopping mall.

3
Default Avatar
EcoConsulting
LEEDuser Basic Member
549 thumbs up
Fri Sep 5, 2014, 2:45 pm

Sampling Locations

NC-v4 EQc4:Indoor air quality assessment
posted by  Courtenay Griffin  on 

Recognizing the issues already under discussion regarding the analytical methods and the maximum contaminant levels presented in LEED v4...

2
Fri Sep 5, 2014, 1:51 pm
2
Fri Sep 5, 2014, 1:32 pm

Natural Ventilation in a Warehouse

EBOM-2009 IEQp1:Minimum IAQ Performance
posted by  Diego Pietzsch  on 

How can a large Warehouse that uses natural ventilation system, but does not meet the requirements of ASHRAE 62.1-2007 section 5.1 be able to pass under the LEED EBOM IEQp1?

2
Default Avatar
Sustainability Consultancy Services
Cushman & Wakefield
LEEDuser Basic Member
11 thumbs up
Fri Sep 5, 2014, 12:08 pm

100% OA multiple-zone system

NC-2009 IEQp1:Minimum IAQ Performance
posted by  Michael Wironen  on 

Hi, I'm a little confused about a review comment we received. We have rooftop AHUs supplying 100% Outdoor Air to multiple zones equipped with terminal fan coil units.

2
Default Avatar
President
Weatherby Design & Co. Engineers
LEEDuser Basic Member
67 thumbs up
Thu Sep 4, 2014, 2:19 pm

LEED IEQ Cr5

LEED Canada Forum
posted by  Peak Longhorn  on 

Hi, I'm working on a project that consists of a large warehouse, drive-in bays and a narcotics storage. Currently I have separate ventilation and exhaust units for each space.

4
Thu Sep 4, 2014, 2:16 pm

Mark LEED v4 credit as ready

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Charalampos Giannikopoulos  on 

Does anyone know how a credit/prerequisite can be marked as "ready" in the new LEED Online (v4)?

2
Thu Sep 4, 2014, 1:05 pm

What does "can include" mean?

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Aron Weis  on 

If there is a non-LEED-certifiable building within the LEED project boundary, the project team can include the non-certifying building within the project boundary in ALL relevant submittals that ar

8
Thu Sep 4, 2014, 4:16 am

Appendix 4 - Case A

CS-2009 WEp1:Water Use Reduction
posted by  Sy Shumaker  on 

We have a CS project with no signed tenants yet. The owner is providing central restrooms and showers for all of tenants in the base CS project.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Wed Sep 3, 2014, 7:39 pm