Help determining Baseline System for Model
CS-2009 EAp2:Minimum Energy Performanceposted by Brian Salazar on
Hello! My first post here on LEED User. We are modeling an existing building which has had its rooftop units replaced "in kind", so they are more efficient units, but the same general makeup.
LEED NC energy model for spaces occupied by other tenants
NC-2009 EAc1:Optimize Energy Performanceposted by Cory Ferguson on
We are designing a 4 story building where the owner will occupy 3-1/2 floors of the building and another tenant will at some point occupy the remaining portion.
Timing of surveys
EBOM-2009 SSc4:Alternative Commuting Transportationposted by American University on
We are dealing with the challenge of surveying commuters on a college campus.
Indirectly Conditioned Bathrooms
NC-2009 EAc1:Optimize Energy Performanceposted by Phillip Cook on
I am using IES VE to model hotel type rooms that each have a separate bathroom. The bathrooms do not have any heating equipment, cooling equipment or thermostats in them.
Circulation space Ventilation
CS-2009 IEQp1:Minimum IAQ Performanceposted by Mike D on
Review comments have asked us to include circulation space in our VRP calculator. However, the corridors in the building will not be served by direct air supply.
Statement Of Energy Performance valid for France ?
EBOM-2009 EAc6:Emissions Reduction Reportingposted by florian Beauchet on
Hi, I'm a french engineer and I'm wondering if the SEP considers the region of the study. Indeed my site is in France, thus does the GHG emissions result use french emission factor ? Same questi
Flush Out using exhaust fans / natural ventilation
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Maya Karkour on
Dear All, Our project is aiming for the Flush-out option of this credit. 1) For the car parking (on the Ground Level), the air is exhausted by dedicated exhaust fans as per ASHRAE 62.1.
Tenant Sales or Lease Agreement
posted by Julie Hendricks on
I have several clients that are nearly refusing to provide a copy of their lease agreements because of concerns over confidentiality.
VAV terminal unit modulation
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Jorge Torres-Coto on
I have a Tenant Improvement that has VAV terminal units connected to an existing VAV AHU. The contractor and owner decided to save money and utilize stand alone control.