Reviewer said that we need to include the PV for our project in the systems manual. The PV was exisitng (previously commissioned) and is owned, operated and maintained by a third party. The building owner will never touch the system because thier contract tells them they can't. It makes no sense to include operation information in the systems manual because it may indicate to the building owner that they can and should mess with the system. I would agree to include a note that the system is part of the building and also include contract contact information but that is it. Would you agree?