Topic | Recent |
---|---|
Owner Letter of CommitmentLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Caitlin Levitsky on Jul 17, 2012, 10:28 am
On the clarification request for multiple credits, we were directed to provide "a signed statement from the Owner indicating that all future fit-outs executed to complete these unfinished space(s... Last reply: Hernando Miranda, Nov 14, 2012, 5:41 pm |
|
Changing compliance path after preliminary reviewLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Matthew Merli on Nov 8, 2012, 1:21 pm
We just received our comments back for our first (preliminary) construction review. It seems we have the points for certification and want to streamline the process as we are NOT anticipating... Last reply: Marcus Sheffer, Nov 8, 2012, 3:42 pm |
|
Name Change in the ProjectLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Michelle Deschaaf on Oct 20, 2011, 3:56 pm
We have a project that we registered with one name and the client decided to change their company name when the project was complete. We are still in the process of filling out all the templates... Last reply: Maria Blake, Nov 7, 2012, 1:10 pm |
|
Split reviews and deductive alternatesLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Lisa Sawin on Nov 6, 2012, 3:19 am
We are in a unique situation where our client requires deductive alternates that total 20% of the project and a minimum of a LEED Silver certification. We would like to do a split design... Last reply: Marcus Sheffer, Nov 6, 2012, 9:56 am |
|
How many times can the appeal be submitted?LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by dia2000@gmail.com dia2000@gmail.com on Oct 10, 2012, 7:32 am
As of my understanding, appeals can be submitted as many times as the project team wishes. Is this true? I mean, if an appeal on a certain credit has been denied by... Last reply: Hernando Miranda, Oct 10, 2012, 10:55 am |
|
Providing a clarification narrative?LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Tim Connor on Oct 1, 2012, 11:11 am
As part of my review comments I have been asked to provide clarification narratives for several MEP related credits. Notably EAp3 has no required uploads, so I can't upload a narrative... Last reply: Marcus Sheffer, Oct 2, 2012, 9:46 am |
|
Submiting a new credit during a clarificationLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Christopher Sawyer on Sep 26, 2012, 2:57 pm
I did a split review under V2.2 and I'm now in Construciton submittal but the reviewers have asked for clarifications. It seems possible to add a design credit not orginally pursued at this time... Last reply: Scott Bowman, Sep 26, 2012, 3:06 pm |
|
Leed NC 2009- documents to translate in english for reviewsLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Nicolas MOLLE on Sep 10, 2012, 12:34 pm
Hello, Last reply: Steve Khouw, Sep 12, 2012, 6:09 am |
|
What happens when you 'skip final design review'?LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Valerie Molinski on Aug 20, 2012, 4:57 pm
I've never been in this situation before, and I don't want to hit the button and 'wait and see.' i have a project where we were doing a split submittal. I submitted for preliminary design... Last reply: USGBC National Office (in DC) BG+LU FW, Aug 21, 2012, 10:30 am |
|
Assigned Team Role: Leed v2.2LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Elle Brown on Jul 30, 2012, 9:41 am
How important is it that the person associated with the 'Assigned Team role" in the Claim of Credit Status matches the name on the uploaded credit template Is it necessary for me to go into each... Last reply: Susan Walter, Aug 20, 2012, 8:13 am |