Forum quick links
Natural Ventilation in a Warehouse
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Diego Pietzsch on
How can a large Warehouse that uses natural ventilation system, but does not meet the requirements of ASHRAE 62.1-2007 section 5.1 be able to pass under the LEED EBOM IEQp1?
100% OA multiple-zone system
NC-2009 IEQp1:Minimum IAQ Performanceposted by Michael Wironen on
Hi, I'm a little confused about a review comment we received. We have rooftop AHUs supplying 100% Outdoor Air to multiple zones equipped with terminal fan coil units.
LEED IEQ Cr5
posted by Peak Longhorn on
Hi, I'm working on a project that consists of a large warehouse, drive-in bays and a narcotics storage. Currently I have separate ventilation and exhaust units for each space.
Mark LEED v4 credit as ready
posted by Charalampos Giannikopoulos on
Does anyone know how a credit/prerequisite can be marked as "ready" in the new LEED Online (v4)?
What does "can include" mean?
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Aron Weis on
If there is a non-LEED-certifiable building within the LEED project boundary, the project team can include the non-certifying building within the project boundary in ALL relevant submittals that ar
Appendix 4 - Case A
CS-2009 WEp1:Water Use Reductionposted by Sy Shumaker on
We have a CS project with no signed tenants yet. The owner is providing central restrooms and showers for all of tenants in the base CS project.
Glazing location for visual access
NC-2009 IEQc8.2:Daylight and Views—Viewsposted by SSN Energy Model on
One of our project (office building), sill height of the glazing is 6.5 feet from finished floor level & glazing height is 3.3 feet. All the regularly occupied spaces are having glazings at th
LEED Project Boundary
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Rezkar Abdulmajeed on
Can someone help me with this please?. I am working now in a health care LEED Project. The LEED Boundary was set already when we submitted the MPR.
MRc4 - Recycle Content of Reinforcement Steel
NC-2009 MRc4:Recycled Contentposted by Keerthi Ratnayake on
How can we use the reinforcement steel towards this credit? Generally, suppliers do not have any information. Can we count 50% straightaway? Thanks
Stormwater rate and quantity calculation for case 1
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by sona prajapati on
Dear all, We have found a sample calculation to determine storm water rate and quantity for 1 yr-24 hr design storm and 2 yr-24 hr design storm from www.illinoisfloods.org/.../4D_Stormwater%20Volum