Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

C&S Building with no HVAC upon initial completion

CS-2009 EAp2:Minimum Energy Performance
posted by  Tony Schafer  on 

This question is related to both EAp2 and EAc5.1.

4
Default Avatar
AtSite
LEEDuser Basic Member
1 thumbs up
Tue Dec 16, 2014, 7:13 pm

Thresholds, Prerequisites, Lease Language, 10102

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Katie Peterschmidt  on 

I am working on a mixed-use building that is required by municipal code to achieve LEED Silver.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Dec 16, 2014, 3:55 am

bus space

NC-2009 PIf2:Project Summary Details
posted by  jorge calderon  on 

The project has visitors from schools that usually arrives in school buses, near the entrance is located a provisional parking space until students leave school bus and then the driver goes to a pa

3
Mon Dec 15, 2014, 11:11 pm

LEED CS Tenant Agreements - Required?

CS-2009 WEp1:Water Use Reduction
posted by  Lawrence Lile  on 

If I understand correctly, if the Core and Shell developer isn't providing plumbing fixtures, then the tenant agreement is essentially required by LEED to dictate plumbing fixtures.

4
LEED Project Reviewer certificate holder
LEEDuser Basic Member
76 thumbs up
Mon Dec 15, 2014, 8:08 pm

MRc2-Concrete Not Poured from Truck and Returned to Batch Plant

NC-2009 MRc2:Construction Waste Management
posted by  Gregg Behmer  on 

Is our leftover concrete, not poured from the truck and returned to the batch plant, counted as diverted from landfills per MR2 if we can provide documentation that it is reused by the batch plant

2
Default Avatar
LEEDuser Expert
472 thumbs up
Mon Dec 15, 2014, 5:10 pm

SSc1, Path 12

CI-2009 SSc1:Site Selection
posted by  David Lauchner  on 

If the building we have selected has an Energy Star rating of 95, can this be submitted for Path 12: Other Quantifiable Environmental Performance?

3
Mon Dec 15, 2014, 3:07 pm
5
Architect & Sustainable Design Consultant, AIA, MRAIC, LEED AP
Design Synergies Architecture
LEEDuser Basic Member
49 thumbs up
Mon Dec 15, 2014, 12:58 pm

Renewable Energy Contract question...

NC-2009 EAc6:Green power
posted by  Rick Alfandre  on 

Our client is trying to sign a 2 year contract for renewable energy, and the company he is engaged with only offers 1 year.

5
Default Avatar
Principal
Alfandre Architecture
LEEDuser Basic Member
13 thumbs up
Sun Dec 14, 2014, 11:29 pm

Residential building above

Retail-CI-v4 EQp2:Environmental Tobacco Smoke Control
posted by  Francisco Sanchez Arroyo  on 

I am thinking of upgrading a v2009 project to V4 but I am concerned if I will meet the requirements of this prerrequisite.

2
Sustainability Manager
YR&G
LEEDuser Basic Member
151 thumbs up
Fri Dec 12, 2014, 11:01 pm

Please Consider Universal Accessibility

Pilot-Credits EQpc78:Design for active occupants
posted by  Jonathan Ramsey  on 

Requirement 5 states "Locate a main staircase to be visible before an occupant visually encounters any motorized vertical circulation (elevator/escalator).

3
Project Manager
A3C Collaborative Architecture
LEEDuser Basic Member
1 thumbs up
Fri Dec 12, 2014, 9:02 pm