NC-2009 EAp2:Minimum Energy Performanceposted by Curtis Clark on
For Non-Residential fenestration system that are designed to be field glazed or field assembled units for compliance with ASHRAE 90.1-2010, the supplier provides a certificate according to NFRC pro
Measuring Flow Rate
CI-2009 WEp1:Water Use Reduction—20% Reductionposted by Robert Calloway on
Hello, We are investigating a building that claims to have reduced flow fixtures installed but this does not seem to be the case.
Water use test report
CI-2009 WEp1:Water Use Reduction—20% Reductionposted by Jatuwat Varodompun on
In case the the manufacturer does not have the cutsheet showing the water data, can we do the on-site measurement and adjust the flowrate to be used in the calculation? We plan to do the elaborate
Innovation and Design - Green Building Education
NC-2009 IDc1:Innovation in Designposted by Rick Alfandre on
We are in between preliminary and final design review, and are thinking of pursuing an I&D credit for Green Building Education.
Are we allowed to used our own developed excel sheets?
NC-2009 IEQp1:Minimum IAQ Performanceposted by Mehdi Kardehi on
Hi All, A quick question. Are we allowed to submit our own calculation spreadsheets of ASHRAE 62.1 or we have to use LEED provided forms to apply for this credit? Cheers, Medi
Densely occupied spaces
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Hi Markus, I'd like to ask you for your opinion and advice about applying these values following the case described below. In LEED glossary such spaces are determined as 25 people per 100 sq ft. W
VRF with DOAS inyecting air into common return plenum
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Zonda E. Team on
Hi there, I'm working on a project with VRF + DOAS, where outside air is injected into a common return plenum for all VRF indoor units.
Energy-Star equivalent products
CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliancesposted by R G on
For one of our overseas project we needed appliances that were 50 Hz; 220-240V.
IEQp1 and Performance Period Timeline
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Jennifer Turchin on
I am working on a number of facilities owned by the same entity and they want to have the outdoor air testing done at all the facilities as one scope of work for a contractor, however, the performa
Renewable Energy entered separately in leedonline form?
NC-2009 EAp2:Minimum Energy Performanceposted by Maya Karkour on
Hello, The thermal modeller scope is limited to detailed design, and at this stage Renewable energy (PV and Solar Water Heating) is still not 100% finalized / decided.