Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

LEED CI -PI FORMS

CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliances
posted by  Yong Lee Low  on 

For our project which is aiming LEED CI, is a floor in an office building , and the building itself is part of a bigger complex comprising of 5 buildings in all. The PI 1 form has ITEM 4 stating "

2
Default Avatar
Principal
Sue Barnett Sustainable Design
LEEDuser Basic Member
96 thumbs up
Mon Dec 19, 2011, 10:28 pm

Energy Star equipment category exemptions?

CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliances
posted by  Amy Mussen  on 

We're working on a LEED-CI office fit-out project in the UK.

5
Sustainability Account Manager
Stok
LEEDuser Expert
177 thumbs up
Mon Dec 19, 2011, 9:46 pm
5
Default Avatar
Graduate Architect, LEED AP
MSKTD & Associates, Inc.
LEEDuser Basic Member
14 thumbs up
Mon Dec 19, 2011, 9:44 pm

Rated Power

CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliances
posted by  Lauren Fakhoury  on 

Is there a way to calculate rated power? I am trying to find the rated power of a printer.

2
President
Sage Building Revival
LEEDuser Premium Member
113 thumbs up
Mon Dec 19, 2011, 8:25 pm

Establishing the LEED Project Boundary

NC-2009 SSc5.2:Site Development—Maximize Open Space
posted by  Robert Mulcahy  on 

I’m trying to confirm the LEED Project Boundary. Normally, the LEED Project Boundary for a single building development would be the same as the site boundary.

2
Mon Dec 19, 2011, 8:24 pm

Tennis Court use for meeting SSc5.2 Maximize Open Space

NC-2009 SSc5.2:Site Development—Maximize Open Space
posted by  JOHN COOK  on 

Can we count count our Tennis courts - that are part of the project boundary towards our Space requirement in Case 2? The courts are hardscaped.

2
Integrated Design & LEED Specialist
SERA Architects
LEEDuser Expert
1361 thumbs up
Mon Dec 19, 2011, 8:17 pm

Glass partition system with aluminium frames

CI-2009 MRc4:Recycled Content
posted by  Yong Lee Low  on 

We are using an interior partition system which includes aluminium frames and glass partitions.The aluminium frames have recycled content but according to the CSI masterformat list do we need to in

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Dec 19, 2011, 7:15 pm

Permeable pedestrian sidewalk

CS-2009 SSc5.1:Site Development—Protect or Restore Habitat
posted by  MARCIO OROFINO  on 

Would anyone inform if permeable pedestrian sidewalk on the ground, recharging groundwater, may be counted towards the achievement of the restored área and ecollogic site feature? Tks

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Dec 19, 2011, 6:52 pm

Repair Bays

NC-2009 IEQc2:Increased Ventilation
posted by  Esperanza Adams  on 

Repair bay do not have Ventilation requirement but they do have exhaust requirement. Per the increased ventilation credit would we have to exhaust 30% more outside air?

2
Principal, Energy and Engineering Leader
DLR Group | Westlake Reed Leskosky
LEEDuser Expert
267 thumbs up
Mon Dec 19, 2011, 4:34 pm

Parking Islands

NC-2009 SSc5.1:Site Development—Protect or Restore Habitat
posted by  Zachary Guren  on 

Has anyone successfully used parking lot islands planted with native vegetation to contribute toward this credit?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Dec 19, 2011, 1:51 pm