Forum quick links
Occupant Default Density vs. Actual density
CS-2009 IEQp1:Minimum IAQ Performanceposted by Maya Karkour on
Hello, we are working on a C&S Mall project, is it permitted that we uncheck the Default density checkbox in IEQp1 form, and enter expected number of persons based on Architects / Engineers ex
data center equipment not listed in DOE Energy Star categories
CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliancesposted by Gail Napell on
Servers are listed on the Energy Star website, but not receivers. Is it safe to assume they are still not Energy Star eligible?
EAc5.1 and EAc5.2
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Christos Alexandrou on
Hello, I have been following the leeduser site and still trying to understand EAc5.1 and EAc5.2. I have been using them differently due to not having a clear explanation of the credits at usgbc.
controllability in addition projects
NC-2009 IEQc6.1:Controllability of Systems—Lightingposted by Saju Varghese on
when I have an addition project do I have to demonstrate compliance for the new addition and renovated areas or does it have to be applied to all areas? (existing to remain, renovated and new)
addition project compliance)
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Saju Varghese on
when I have an addition project do I have to demonstrate compliance for the new addition and renovated areas or does it have to be applied to all areas? (existing to remain, renovated and new)
Addition Project
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Saju Varghese on
when I have an addition project do I have to demonstrate compliance for the new addition and renovated areas or does it have to be applied to all areas?
addition on an area
EBOM-2009 MRc4:Sustainable Purchasing—Reduced Mercury in Lampsposted by Saju Varghese on
when I have an addition project do I have to demonstrate compliance for the new addition and renovated areas or does it have to be applied to all areas? (existing to remain, renovated and new)
Historic district
NC-v4 LTc3:High priority siteposted by Pia Öhrling on
Is option 1 viable if you demolish a non-listed building in a historic district and build a new one in its Place?
3% refueling for future Retail-CI tenant
posted by Katie Peterschmidt on
Our LEED-NC project is required to provide tenant guidelines per CIR 10102.
pressure differential
NC-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Courtney Royal on
How are people proving the differential pressure of applicable spaces in credit documentation?