Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Disinterested Sub-contractor of MEP Design Firm?

NC-2009 EAc3:Enhanced Commissioning
posted by  Anthea Ng  on 

Hello. For achieving EA C3 Enhanced Commissioning, Wwe noted the clause in guidebook "Must not be an employee of the design firm, though he or she may be contracted through them".

1
Fri Jun 13, 2014, 12:37 pm

Ventilation - Proposed and Baseline per ASHRAE 62.1-2007?

NC-2009 EAp2:Minimum Energy Performance
posted by  Todd Tewksbury  on 

Hi! I am conducting a LEED v2009 EAp2/c1 energy model for a nonresidential building that is more than 5 floors.

1
Tue Jun 17, 2014, 1:46 pm

Expansion project FLUSH OUT

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Jorge Torres-Coto  on 

We have a project that is an expansion to an existing facility. It is NOT an addition.

0

Submitting for Review & Terminolgy

Living with LEED Online - quirks, bugs and hiccups
posted by  Charles Nepps  on 

Just submitted a CI v2009 project for final (combined) review. Initially I was getting error messages that it could not be submitted unless all Prereqs & Credits were marked "complete".

1
Mon Jun 16, 2014, 9:23 am

Multi zone or 100%OA ?

NC-2009 IEQp1:Minimum IAQ Performance
posted by  SW LEE  on 

Our project is use VRF system to keep the space cool. We also provide dedicated injection fan (DOAS) as to meet 62.1 requirement. Most space will have indoor cassette unit.

1
Tue Jun 17, 2014, 3:06 pm

LEED AP BD+C after LEED GREEN ASSOCIATE EXAMS

General forums
posted by  GOVINDACHARI SUNDARARAJAN  on 

Dear sir/Madam, I have passed LEED-Green Associate Exam on June-13th 2014, i am planning to takeup LEED AP BD+C in the next 3 months, i have a query as below, if i take up LEED AP BD+C, is it tha

0

Increasing the indoor operative temperature

NC-2009 IEQc7.1:Thermal Comfort—Design
posted by  Stella Stella  on 

Hi, we are doing a project in South east Asia for LEED NC.

1
Wed Jun 25, 2014, 12:53 am

Off-Site Parking

NC-2009 PIf2:Project Summary Details
posted by  Mary Kay  on 

My project is new construction - a hangar at an airport that will be used for painting jet airplanes. The owner already has previously built a building adjacent to our site with a parking lot.

1
Mon Jun 16, 2014, 7:20 pm

Freight and tax on wood invoices

NC-2009 MRc7:Certified Wood
posted by  Renee Shirey  on 

The wood invoices that I have show a separate line item for tax/fuel charge/freight charges, etc. and I was unclear how to include this in the documentation.

1
Tue Jun 24, 2014, 6:38 am

EBOM 2009 EAp1 L-9 upload document

EBOM-2009 EAp1:Energy Efficiency Best Management Practices
posted by  James Doyle  on 

The credit template form for EBOM 2009 EAp1 on page 2 requests "Upload L-9. Provide a breakdown of total project building annual energy consumption by major end uses or applications.

1
Tue Jun 17, 2014, 1:06 pm