Forum quick links
IRA Update
posted by Cory Duggin on
Following up on conversation from the Fika today, Kim said the IRS is supposed to be issuing rules for tax-based (even for orgs that don't pay tax) credits by the end of first quarter. Sounds
Clear opening width for doors
Pilot-Credits INpc125:Inclusive Designposted by Jennifer Atherton on
Hello,
Does the requirement for 0.91 meter wide interior doors refer to the minimum effective clear width through the doorway?
Credits that require energy metering
EBOM-v4.1 EAp1:Energy Efficiency Best Management Practicesposted by Ricardo Filho on
Hi all
hope you are having a great start of 2023!
regional priority credits V4.1 New Construction
NC-v4.1 RPc1:Regional Priorityposted by Angela Loughry on
Hello-
PHIUS Certification
Pilot-Credits IPpc100:Passive Survivability and Back-up Power During Disruptionsposted by Neil Rosen on
Regarding Option 1 Path 3 - What Certification from PHIUS will satisfy this pilot credit? Design or Final? It would seem that Design would be all that should be required as Paths 1 &
Credit Substitution Point Mismatch
NC-v4.1 SSc4:Rainwater Managementposted by Grace Friedhoff on
We are registered as a v4 project but would like to substitute the Rainwater Management credit for version 4.1. However the credit thresholds do not update in LEEDonline when you substitute.
Canadian ACP - NECB ASHRAE Exceptions Clarification
NC-v4 EAp2:Minimum energy performanceposted by Kristina K on
Hello,
Medical Office Building - Exam | Soiled/Clean Workroom | Mop Sinks - What fixture should these be listed as on the form?
NC-v4.1 WEc2:Indoor Water Use Reductionposted by Catherine Blakemore on
I am working on a LEED v4.1 BD+C Medical Office Building project and trying to complet the WEc1 form. There are no fixture options for for the following fixtures: