Multi-family - Energy Disclosure Requirement
NC-2009 MPR6:Must commit to sharing whole-building energy and water usage dataposted by Jeremy Kuhre on
Courtney, we have a similar situation to yours in that we do not have access to whole building utility data. We are currently in the process of certifying several large multi-family projects under
Modified AHU
CI-2009 EAp2:Minimum Energy Performanceposted by Silvia Ruiz on
Hi, If an AHU (initially outside of the scope of work) had to be modified in order to comply with the ventilation requirements of Standard 62.1-2007, does it have to comply with the requirements
non certifiable building
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by renee jimenez on
what is the definition of a non-LEED-certifiable building? does it mean your not going to attempt to certify them or that they dont qualify/meet minimum requirements?
Fly Ash
CS-2009 MRc3:Materials Reuseposted by Jeremy Theodore on
Same question, but I assume fly ash used in concrete is considered recycled content?
Can a LEED-NC project be added LATER to a master site future?
posted by Alice Sung on
Question: I have new LEED-NC project for a building on a college campus.
1/2 mile distance to basic services..
NC-2009 SSc2:Development Density and Community Connectivityposted by Hanne Goa on
Our project is located within 1/2 mile radius of more than 10 basic services. There is pedestrian access between the building and the services.
HAP boiler input data
NC-2009 EAp2:Minimum Energy Performanceposted by PAWAN DAHIWAL on
is estimated max load reported in HAP boiler input data for baseline case same to that of total heating capacity reported in Table 1.4 HVAC (water side) for baseline???. In one of the project Est
Manufacturing facility: heat recovery and cooling of compressors
NC-2009 EAc1:Optimize Energy Performanceposted by Johannes Gellrich on
Dear all, I have a large manufacturing facility with an associated office wing, on which I would like to discuss two things: 1.
Unknown CFM into spaces
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Sonrisa Lucero on
We are using the 62MZ Calculator spreadsheet for an office building. The HVAC system does not utilize VAV boxes or any kind of terminal unit. Rather, it just feeds directly into each space.
Measuring the landscaped area
NC-2009 WEc1:Water Efficient Landscapingposted by Alicia Villanueva on
We are trying to reach the 5% landscaped area in a project. The question is: how do we measure it? The shaded area or the tree well area? Thank you!