posted by Bryan Pratt on Oct 10, 2012, 9:56 am

I am currently working on a building whose main function will be for painting and which will contain several large paint booths. Over 90% of the energy expended by the building will be to...

Last reply: Marcus Sheffer, Oct 11, 2012, 11:35 am

ashrae 90.1 2007- space type

CI-2009 EAp2: Minimum Energy Performance
posted by gustavo goldman on Oct 6, 2012, 2:32 pm

The selling area of a retail commercial interior project will be a conditioned space located over a parking area whose height is half under sidewalk level and half above it. This happens on 2 of...

Last reply: Marcus Sheffer, Oct 9, 2012, 12:04 pm

Permanently Dimmed LED Lamps

CI-2009 EAp2: Minimum Energy Performance
posted by Luis Miguel Diazgranados on Sep 28, 2012, 6:24 pm

Greetings Everyone,
We are working in a CI project, in which, by error, the lightning contractor obtained some LED bulbs with a larger wattage than the lightning designer specified wattage...

Last reply: Luis Miguel Diazgranados, Oct 4, 2012, 1:22 pm

ASHRAE Lighting Compliance Documentation

CI-2009 EAp2: Minimum Energy Performance
posted by Luis Miguel Diazgranados on Aug 31, 2012, 10:56 am

Greeting to everyone,

For this prerrequisite's form, LEED asks to upload ASHRAE's "Lighting Compliance Documentation". I have been trying to fill in the tables within this PDF, but there...

Last reply: Luis Miguel Diazgranados, Aug 31, 2012, 12:25 pm

EA Prerquisite 2 compliance for International Project

CI-2009 EAp2: Minimum Energy Performance
posted by gustavo goldman on Aug 15, 2012, 2:56 pm

Due to restrictions of the imports set by the National Government early this year, there are no HVAC systems

Last reply: Marcus Sheffer, Aug 15, 2012, 3:21 pm

LEED CI project in China

CI-2009 EAp2: Minimum Energy Performance
posted by Diana Hill on Aug 4, 2012, 7:09 pm

Hello,

We are doing a LEED CI project in China. This is a office building with two 16-floors buildings A, B and a 9-floors building C, which are connected by a 7-floors podium. The project...

Last reply: Marcus Sheffer, Aug 6, 2012, 8:54 pm

Project in Europe and Energy Star

CI-2009 EAp2: Minimum Energy Performance
posted by Maria Porter on Apr 13, 2012, 7:04 am

I’m starting to realize that it will be hard to find Energy Star rated equipment in Sweden. Computers – no problem, but for fridges, dishwashers etc we use the European EU energy rating system....

Last reply: Bill Swanson, Aug 2, 2012, 8:48 am

HVAC Control

CI-2009 EAp2: Minimum Energy Performance
posted by Carolina Vergnano on May 15, 2012, 12:44 pm

Hello,

I'm working in a project that has 2 meeting room of 7 m2 next to each other and one of meeting room is exposed to exterior window.
My doubt is, do I have to install a separate...

Last reply: Marcus Sheffer, May 25, 2012, 9:02 am

Detailed Plant Simulation

CI-2009 EAp2: Minimum Energy Performance
posted by Chilufya Lombe on May 25, 2012, 3:11 am

Hi, we have a project with a certain number of 'back up' systems for air conditioning. The main system is a geothermal ground loop but there is an air cooled chiller that will be installed as...

Last reply: Marcus Sheffer, May 25, 2012, 8:29 am

EAp2-2 90.1 HVAC Compliance Forms

CI-2009 EAp2: Minimum Energy Performance
posted by George Bender on May 10, 2012, 11:09 am

When completing page 1 the HVAC Mandatory Provisions nothing applies with exception to the Load Calcs and construction docs check columns because the central plant serving this floor is outside...