Log in
Forum » EBOM-2009 EAc1
Topic

Protfolio Manager Analysis

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Paola Figueiredo, Newton Figueiredo on Aug 4, 2011, 3:34 pm

We are working on projects for LEED EBO&M and have some doubts related to the credits EApre1& EAc1. The Portfolio Manager Analysis is unable to classify the energy consumption of the...

Last reply: Alexa Stone, Aug 10, 2011, 5:08 pm

EAp2 Case 2B Fulfillment

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Jessica Bruscato on Aug 10, 2011, 12:23 pm

Being that my project is a convention center, it does not qualify for energy star. Therefore, I am using the EAp2 Case 2 offline calculator in conjunction with the EPA portfolio manager tool...

Last reply: Alexa Stone, Aug 10, 2011, 5:03 pm

Sharing the Portfolio Manager facility profile

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Carrie Bradley on May 3, 2011, 3:15 pm

LEED EBOM v2009...

Last reply: Carrie Bradley, Jun 22, 2011, 10:16 am

Case 2 Option 2 (A, B, C)

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Marc Mondor on Jan 18, 2011, 12:50 pm

All,

We are working on a unique facility (production greenhouse) which based on my understanding of EA Pre1 Cr2 can only meet this prerequisite using Case 2 options B--historical data and...

Last reply: Raphael Sperry , May 23, 2011, 7:08 pm

LEED-EBOM District Energy Systems (DES) guidance available

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Tristan Roberts on Dec 22, 2010, 12:01 pm

Yesterday USGBC posted posted key guidance for your project if it involves a...

Last reply: Alexa Stone, Mar 25, 2011, 4:35 pm

Maximum Points Available

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by David Hubka on Mar 24, 2011, 5:14 pm

The LEED O&M reference guide states that two points are available under EA Credit #1 for projects that follow Case 2 Option 2A however the LEED online template does not award credits under...

Last reply: Jenny Carney, Mar 25, 2011, 2:14 pm

Office building, Jeddah, Saudi A

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Lise Dannesboe on Feb 21, 2011, 8:31 am

We have established a rating for the building based on Case 2 Option 1 - beacause the building is not eligible for an Energy Star rating. Based on last years energy data the EA Credit 1 Case 2...

Last reply: Marc Mondor, Mar 8, 2011, 5:56 pm

Natural Gas Use

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Alexa Stone on Dec 13, 2010, 12:18 pm

We are certifying a building in a campus. The campus as two commercial kitchens, one being in the building we are certifying. Typically, only the kitchen in the project building is used for all...

Last reply: Dan Ackerstein, Jan 21, 2011, 5:58 pm

LEED EBOM Case 2, Option 1

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Jennifer Turchin on Jan 17, 2011, 1:21 pm

The project we are working on is a 170,000 SF plus vitamin manufacturing facility with over 10% laboratory space. It does not qualify for an ENERGY STAR rating given too much "other" space....

Last reply: Jenny Carney, Jan 21, 2011, 11:25 am

Old building pursuing GBOM- CIR for an exception on EA1

EBOM-2009 EAc1: Optimize Energy Efficiency Performance
posted by Tom Kennedy on Oct 13, 2010, 2:18 pm

our building is really old (way older than me), contains ACM's, masonry walls with no insulation, construction of a by-gone era...... it seems unfair to compare it with EnergyStar (...

Last reply: Michael Miller, Dec 7, 2010, 9:02 pm