Log in
Forum » NC-2009 EAc5
Topic

M&V data reporting

NC-2009 EAc5: Measurement and Verification
posted by Joseph Greene on Mar 18, 2011, 4:35 pm

Please verify the reporting period is 1 year and not 2. Your sample M&V plan talks about a two year M&V period.
Are templates available for data reporting and is there a required...

Last reply: Marcus Sheffer, Mar 18, 2011, 5:40 pm

Guidance on the metering part of this credit

NC-2009 EAc5: Measurement and Verification
posted by Barbara McCrary on Jul 14, 2010, 2:36 pm

I'm new to this site, and while not new to LEED projects have never pursued EA Credit 5. The more I dig into it the more vague everything becomes, and more confused I get! Is it required...

Last reply: Marcus Sheffer, Mar 10, 2011, 8:14 am

Monitoring in a multi residential complex

NC-2009 EAc5: Measurement and Verification
posted by lance mccardle on Feb 24, 2011, 3:26 pm

How is this credit addressed in a multi residential complex (77 student apartments) where tenants pay their own energy bills?

Last reply: Marcus Sheffer, Mar 10, 2011, 8:07 am

M&V and metering

NC-2009 EAc5: Measurement and Verification
posted by Emil Cuevas on Nov 18, 2009, 12:12 pm

pressure, fan status etc. As this forum seems more up to date on M&V do you think its possible to not measure all the items listed and focus on what really is important? Log in or register to post...

Last reply: Marcus Sheffer, Mar 10, 2011, 7:56 am

M&V for MURB/retirement home

NC-2009 EAc5: Measurement and Verification
posted by Brian Farrelly on Nov 30, 2010, 4:00 pm

I'm in the process of creating a M&V plan for a retirment building which is basically a MURB. Determining what to meter on the central plant is relative straight forward, however the problem...

Last reply: Marcus Sheffer, Dec 1, 2010, 9:50 am

M&V For Industrial Facilities

NC-2009 EAc5: Measurement and Verification
posted by Mary Frances Stotler on Oct 14, 2010, 11:31 am

We're designing a food processing plant that will have systems in place to monitor the overall loads of the entire building. The drives read the information from all MCCs and determine the...

Last reply: Marcus Sheffer, Oct 14, 2010, 12:07 pm

Re-calibration & corrective action

NC-2009 EAc5: Measurement and Verification
posted by Jenny Stadelmann on Aug 20, 2010, 2:27 pm

Does the re-calibration of the as-built design energy model and the baseline model need to be done monthly during the 12 mos. M&V period, and then corrective action taken monthly based on how...

Last reply: Marcus Sheffer, Aug 20, 2010, 3:15 pm

Metered Energy Use

NC-2009 EAc5: Measurement and Verification
posted by Rebecca Molldrem on Aug 9, 2010, 9:12 am

The credit requirements say, "The M&V period must cover at least 1 year of post-construction occupancy". This however, isn't saying that we can't complete this credit until one year after...

Last reply: Marcus Sheffer, Aug 19, 2010, 4:41 pm

Useful information regarding the issues with this credit...

NC-2009 EAc5: Measurement and Verification
posted by Michael Wymant on Jun 23, 2010, 2:39 pm
Last reply: Carey Paul, Aug 9, 2010, 6:56 pm

Just the Plan?

NC-2009 EAc5: Measurement and Verification
posted by Jean Marais on May 19, 2010, 6:11 am

I've just checked the LEEDonline submittal form for this credit (which by the way mentions a previously unknown EAp2: Minimize Energy Performance prerequisite, ha, ha) which has the following...

Last reply: Tristan Roberts, May 20, 2010, 2:15 am