DHW limitationsNC-2009 EAp2: Minimum Energy Performanceposted by Jorge Lopez de Obeso on Jan 16, 2019, 1:25 pm
Hi, I've been having some trouble regarding... Last reply: Jorge Lopez de Obeso, Jan 22, 2019, 5:01 pm |
|
Building connected to CCHP plant- Energy performance results reportNC-2009 EAp2: Minimum Energy Performanceposted by Ricardo Sá on Jan 16, 2019, 10:02 am
Hi, we're currently working on a project that is connected to a CCHP plant. HVAC thermal needs (cooling and heating) are supplied by the referred plant. Due to this, in terms of energy... Last reply: Marcus Sheffer, Jan 22, 2019, 11:23 am |
|
Using Trane Trace for Solar PV ModelingNC-2009 EAp2: Minimum Energy Performanceposted by Bo White on Jan 11, 2019, 6:53 pm
Our building will have on-site (and dedicated campus) solar PV, and we're using Trane's Trace program for our ASHRAE 90.1 energy model. However, Trace doesn't seem to have one definitive solar PV... Last reply: Marcus Sheffer, Jan 14, 2019, 2:30 pm |
|
Credit for Biofuels in EA p2 and EA c2NC-2009 EAp2: Minimum Energy Performanceposted by SAMY Chamy on Dec 18, 2018, 4:17 am
Dear All, Good Day ! We have used agricultural waste - rice husk as biofuel in Steam boiler. We have enough documents to claim it in... Last reply: Marcus Sheffer, Jan 7, 2019, 1:14 pm |
|
Proposed case fans cycling with loads during occupied hoursNC-2009 EAp2: Minimum Energy Performanceposted by Gurneet Singh on Nov 12, 2018, 8:27 am
We are working on a residential project in climate zone 4A served by water loop heat pump system for heating and cooling. The baseline system is PTAC with fans running continuously throughout the... Last reply: Jean Marais, Dec 12, 2018, 4:58 am |
|
On-site energy generation for EAp2 minimum energy performance complianceNC-2009 EAp2: Minimum Energy Performanceposted by Gurneet Singh on Dec 11, 2018, 7:24 am
Hello everyone, We are working on campus project with two buildings. For compliance of minimum energy performance, the individual building compliance is required as per multiple buildings... Last reply: Marcus Sheffer, Dec 11, 2018, 9:57 am |
|
Energy Performance Calculator- Group ApproachNC-2009 EAp2: Minimum Energy Performanceposted by Praveenbabu Rajkumar on Dec 10, 2018, 5:40 am
Hi All, We are working in LEED NC v2009 project which is having multiple buildings and the project is going Group approach method. Now we are trying to fill energy performance... Last reply: Marcus Sheffer, Dec 10, 2018, 12:38 pm |
|
Existing Building Glazing DetailsNC-2009 EAp2: Minimum Energy Performanceposted by John on Nov 30, 2018, 8:22 am
Dear all, I'm working on modeling of existing library building. I don't have existing glazing details. Do I have to go for unlabeled vertical fenestration (table 8.2 of ASHRAE 90.1... Last reply: Marcus Sheffer, Nov 30, 2018, 9:59 am |
|
Baseline HVAC System TypeNC-2009 EAp2: Minimum Energy Performanceposted by Michael Hammond on Nov 22, 2018, 5:23 am
Hi all, When selecting the baseline HVAC system type via Table G3.1.1.A, does the fuel source for service water heating also need to be taken into consideration? For example, the proposed... Last reply: Michael Hammond, Nov 26, 2018, 4:10 am |
|
Building system types vs square footage and non-predominant usesNC-2009 EAp2: Minimum Energy Performanceposted by Richard Mathews on Jul 11, 2012, 5:31 pm
I'm working on a project that totals approximately 178,000 sf, of which approximately 140,000 sf is office space (3 stories tall), with the other 38,000 sf being conditioned manufacturing space.... Last reply: Marcus Sheffer, Nov 20, 2018, 1:35 pm |