Log in
Forum » NC-2009 EAp2
Topic

Exterior lighting allowance

NC-2009 EAp2: Minimum Energy Performance
posted by Haojie Wang on Mar 11, 2015, 11:27 am

We have a project that specified exterior lgithing for 1120 W. Based on IECC, we could claim...

Last reply: Marcus Sheffer, Mar 11, 2015, 12:07 pm

System 8 VAV + PFP boxes

NC-2009 EAp2: Minimum Energy Performance
posted by Giuseppina Amorusi on Mar 10, 2015, 9:43 am

Dear All,
We are modelling a Baseline Building with System 8 “VAV + PFP boxes” using HAP by Carrier.
We are wondering how to model the...

Last reply: Giuseppina Amorusi, Mar 10, 2015, 11:08 am

Precision Air Conditioning for Server Room and Art Gallery

NC-2009 EAp2: Minimum Energy Performance
posted by Panupant Phapant on Mar 4, 2015, 9:31 am

Dear All
We have two projects that are attempting LEED 2009 NC Certification the first one is office building with server room and the second one is Arg Gallery. Both projects use precision...

Last reply: Panupant Phapant, Mar 5, 2015, 9:34 pm

Plant Design for Proposed bldg

NC-2009 EAp2: Minimum Energy Performance
posted by Julian Park on Mar 3, 2015, 8:48 am

If a new building will be served by an existing chiller plant that already serves an existing building, does the Plant design for the Proposed Alternative need to model the full chiller size,...

Last reply: Marcus Sheffer, Mar 5, 2015, 12:35 pm

District virtual rate:

NC-2009 EAp2: Minimum Energy Performance
posted by Haojie Wang on Mar 2, 2015, 1:58 pm

We have project using district steam. We use...

Last reply: Marcus Sheffer, Mar 5, 2015, 12:14 pm

District steam

NC-2009 EAp2: Minimum Energy Performance
posted by Haojie Wang on Mar 3, 2015, 4:57 pm

If we convert district steam to hot water for space heating, is there any guideline on the efficiency (of heat exchanger) for baseline model? Or do we assume the efficiency is 100% for both...

Last reply: Jean Marais, Mar 4, 2015, 11:35 am

G3.1.10 (d) "Heating only System"

NC-2009 EAp2: Minimum Energy Performance
posted by Anil Bhari on Feb 27, 2015, 9:37 am

Based upon G3.1.10 (d) “Where no cooling system exists or no cooling system has been specified, the cooling system shall be identical to the system modeled in the baseline building”

Does...

Last reply: Marcus Sheffer, Feb 27, 2015, 4:51 pm

Saving percentage round up to the nearest integer?

NC-2009 EAp2: Minimum Energy Performance
posted by Haojie Wang on Feb 25, 2015, 9:08 am

Will LEED round up the saving percentage to the nearest integer? e.g. 19.8% to 20%? Thanks in advance

Last reply: Haojie Wang, Feb 27, 2015, 9:34 am

Task light process load or lighting load?

NC-2009 EAp2: Minimum Energy Performance
posted by Haojie Wang on Feb 26, 2015, 9:52 pm

I saw some people say task light is process load but sometimes it can be count into lighting power. I wonder is there a good way to treat task light? For my project specifically, the task light...

Last reply: Jean Marais, Feb 27, 2015, 1:16 am

Baseline Return/Relief Fan Power

NC-2009 EAp2: Minimum Energy Performance
posted by Haojie Wang on Feb 23, 2015, 2:05 pm

90.1 AppG G3.1.2.8 says the return/relief fan should be sized for max (SA-OA, 90%*SA) [cfm]. But in table 1.4. the allowable fan power is only based on the supply fan power. If I calculate the...

Last reply: Marcus Sheffer, Feb 24, 2015, 10:20 am