Exemptions to ASHRAE 90.1- 2010NC-2009 EAp2: Minimum Energy Performanceposted by Maria Fiorelli on Nov 13, 2012, 10:34 am
Hello all, We're working on a project that has an area that is includeded under exemptions to ASHRAE 90.1-2010 Interior Lighting Requirements. I'm wondering if anyone out there has seen a... Last reply: Marcus Sheffer, Nov 13, 2012, 10:51 am |
|
Outdoor Air Intake: Baseline vs. ProposedNC-2009 EAp2: Minimum Energy Performanceposted by Ricardo Sá on Nov 12, 2012, 9:07 am
We are currently working on a LEED project whose Baseline Building will have an HVAC system 5 installed. Taking into account that section G3.1.1 of ASHRAE 91.1-2007 states that “for systems 5, 6... Last reply: Marcus Sheffer, Nov 12, 2012, 9:46 am |
|
UnmetLoadHours- Do we have clarity yet?NC-2009 EAp2: Minimum Energy Performanceposted by Jean Marais on Nov 7, 2012, 7:22 am
The definition of Unmet Load Hours has been vague for quite some time. ASHRAE 90.1 2010 was supposed to address this issue. Do we have some resolution about this yet? For example: Last reply: Marcus Sheffer, Nov 9, 2012, 3:17 pm |
|
EQUIPMENT CAPACITY OVERSIZINGNC-2009 EAp2: Minimum Energy Performanceposted by PAWAN DAHIWAL on Nov 9, 2012, 1:48 am
I AM BEGINEER IN THIS FIELD. I HAVE A LITTLE DOUBT ABOUT EQUIPMENT CAPACITY OVERSIZING. Last reply: Marcus Sheffer, Nov 9, 2012, 10:22 am |
|
Baseline Lighting Power densityNC-2009 EAp2: Minimum Energy Performanceposted by Zonda E. Team on Nov 7, 2012, 8:31 pm
Hi, Can you help with the following two issues: Last reply: Marcus Sheffer, Nov 8, 2012, 1:59 pm |
|
Brewery Process Load- Baseline and Proposed Case Set-upNC-2009 EAp2: Minimum Energy Performanceposted by Xun Jia on Nov 7, 2012, 11:48 am
The brewery I am modeling has large percentage of energy consumption associated with the process load. From past posts I understand I need to write a thorough narrative explaining the standard... Last reply: Marcus Sheffer, Nov 7, 2012, 5:58 pm |
|
Energy modeling- ASHRAE §G3.1.2.4NC-2009 EAp2: Minimum Energy Performanceposted by Julien Daclin on Nov 6, 2012, 3:16 pm
Hi all, Last reply: Marcus Sheffer, Nov 7, 2012, 11:16 am |
|
District Cooling- Mandatory ComplianceNC-2009 EAp2: Minimum Energy Performanceposted by Marina Andrade on Oct 16, 2012, 12:16 pm
Hello, I would like to know if the District Cooling System needs to comply with ASHRAE mandatories. I have read the... Last reply: Marcus Sheffer, Nov 6, 2012, 9:38 am |
|
LPD- SI vs IPNC-2009 EAp2: Minimum Energy Performanceposted by Marcus Sheffer on Nov 1, 2012, 5:32 pm
My turn - a question for those of you who have the SI version of 90.1. Is the lighting power... Last reply: Rudolph Carneiro, Nov 3, 2012, 5:50 pm |
|
Updating the LEEDOnline form after being acceptedNC-2009 EAp2: Minimum Energy Performanceposted by Maya Karkour on Oct 31, 2012, 11:04 am
Dear All, If the USGBC awards 4 points under EA Credit 1, but then the design team decides to add significant lighting to the project which will increase the Proposed consumption (and... Last reply: Marcus Sheffer, Nov 2, 2012, 9:33 am |