EA Pre-requ. #1NC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Jason Dohl on Sep 4, 2009, 1:45 pm
I am gearing up to put a Design-Build team together for a 6000 SF commercial building and our goal is Silver. To achieve the pre-req, can our Commissioning Authority be an experienced Design-... Last reply: Ameet AA, Jan 11, 2012, 5:48 am |
|
Systems ManualNC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Michael Lofroos on Sep 30, 2011, 8:47 am
Although it is the requirement of the Commissioning Agent to develop the Systems Manual, Operation & Maintenance Systems manuals, can he/she delegate that responsibility to the General... Last reply: Chris Ladner, Nov 18, 2011, 11:13 am |
|
Commissioned SystemsNC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Dave Madsen on Nov 17, 2011, 10:28 am
I have a question regarding the commissioned systems. If you put in your initial scope the standard energy related systems for... Last reply: Chris Ladner, Nov 18, 2011, 9:55 am |
|
NEBB Certification Required?NC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Nathan Lee on Sep 8, 2011, 8:48 pm
A question about NEBB Certification. Is the... Last reply: Tristan Roberts, Sep 26, 2011, 9:58 pm |
|
Required Number of Construction Inspections?NC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Benjamin Tressler on Sep 19, 2011, 11:19 am
Does LEED specify a required number of... Last reply: Tristan Roberts, Sep 26, 2011, 9:52 pm |
|
Qualification of CxANC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by James Chueh on Aug 7, 2011, 11:24 pm
Quick question, can the contractor of building's BAS (for both the installation and manufacturer of DDC/control components) be designated to be the... Last reply: Lannie Farmer, LEED AP BD&C; QCxP, Aug 8, 2011, 11:40 am |
|
Equipments to be commissionedNC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Alvaro Valdivia on Jul 31, 2011, 2:54 am
Hi: I have a boubt about the water heating equipment to be commissioned. In a production plant there are two boilers (water heating and steam), and heat recovering (to heat water) from three... Last reply: Scott Bowman, Aug 1, 2011, 10:19 am |
|
what happens when verification turns up changes?NC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Tristan Roberts on Jul 20, 2011, 2:33 pm
It's a requirement for EAp1 that the... Last reply: Susann Geithner, Jul 22, 2011, 5:53 pm |
|
Language of DocumentsNC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Catalina A on Jun 8, 2011, 5:49 pm
Does anyone know how the documents and technical specifications of the different projects (HVAC, Electricity, Lighting, hot water, etc.) have to be presented to the... Last reply: Tristan Roberts, Jun 28, 2011, 1:01 pm |
|
Basis of Design (BOD)NC-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by Peter Doo on Jun 28, 2011, 9:06 am
Lately, engineers have been submitting their specifications as the Basis of Design document. We haven't submitted any for review yet but this has occurred several times by different engineers. Is... Last reply: Scott Bowman, Jun 28, 2011, 10:02 am |