Date Stamped PhotosNC-2009 SSp1: Construction Activity Pollution Preventionposted by Maya Karkour on Apr 2, 2012, 8:13 am
Dear all, There are many cameras which do not print a datestamp on the photos (new cameras usually save the date in the photo properties). Can the person who captures the photos,... Last reply: Samantha Harrell, Apr 2, 2012, 11:07 am |
|
Air Pollution PreventionNC-2009 SSp1: Construction Activity Pollution Preventionposted by Ellen Mitchell on Mar 20, 2012, 5:03 pm
This week I have had two projects returned to me from the preliminary construction review with the same comment. I have never seen this comment before and am a little perplexed. The comment... Last reply: Allen Cornett, Mar 27, 2012, 10:30 am |
|
Level of detail needed in ESC?NC-2009 SSp1: Construction Activity Pollution Preventionposted by Patty Breech on Feb 13, 2012, 8:26 pm
This is vaguely referenced in other posts, but I'm still confused: what is the level of detail we need to submit for our written Erosion & Sedimentation Control (... Last reply: Jhoan Montano, Feb 29, 2012, 1:13 pm |
|
A client with ongoing site works asks about LEED feasibilityNC-2009 SSp1: Construction Activity Pollution Preventionposted by Mauricio Ramirez on Jan 25, 2012, 10:13 am
The owner of a project is considering the possibility of the project to become LEED Certified. The current works on site include a excavation of a hill, and the works had been conducted following... Last reply: Tristan Roberts, Feb 24, 2012, 11:35 am |
|
Late implementation no.2NC-2009 SSp1: Construction Activity Pollution Preventionposted by Anna Korinkova on Jan 19, 2012, 4:03 am
Hello all, |
|
NC Major Renovation with minimal site disturbanceNC-2009 SSp1: Construction Activity Pollution Preventionposted by Monika Mickute on Jan 13, 2012, 4:09 pm
Dear LEEDUsers, We are working towards certifying our own office building (an existing 50 year old, single story... Last reply: Steve Loppnow, Jan 16, 2012, 11:56 am |
|
ESC control: flat land, low water mantle and no drainage sewerNC-2009 SSp1: Construction Activity Pollution Preventionposted by marisol cano on Nov 1, 2010, 8:13 pm
Hello. Last reply: Steve Loppnow, Dec 15, 2011, 7:23 pm |
|
Cleared land- How to consider stockpilling?NC-2009 SSp1: Construction Activity Pollution Preventionposted by Gabriela Hernández Castillo on Dec 20, 2010, 11:36 pm
If a site has been bought with all vegetation removed by the previous owner the stockpiling will not longer be available because the site has been already clared-out of any existing vegetation,... Last reply: Steve Loppnow, Dec 15, 2011, 7:18 pm |
|
BMPs from Stormwater Management Manual for Western WashingtonNC-2009 SSp1: Construction Activity Pollution Preventionposted by Jutta Berns on May 24, 2011, 9:48 am
for SSp1 would it be acceptable to choose BMPs from the Stormwater Management Manual for Western Washington, which is referenced for the GIBp4 prerequisite in LEED Neighborhood Development? or do... Last reply: Steve Loppnow, Dec 15, 2011, 6:40 pm |
|
ESC Plan and CAPP Plan for Sloped SiteNC-2009 SSp1: Construction Activity Pollution Preventionposted by Arub Vijay on Nov 8, 2011, 8:20 am
We have a Hotel project which will be constructed on a mountain with the whole site having a slope towards west. The 8 storied building is flush with the mountain such that only one or two sides... Last reply: Steve Loppnow, Dec 15, 2011, 6:35 pm |