Forum quick links
C&S ventilation
CS-2009 IEQp1:Minimum indoor air quality performanceposted by Randy Cook on
Hello. I'm working on a C&S project and have a question regarding the documentation of the IEQp1 credit. During the design a single tenant was found to occupy the entire site (700k sf).
Breathing zone ventilation
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Rudolph Carneiro on
Must Vbz be met for all zones in a multizone system? Section 6.2 states that the VRP procedure is for determining Vot and not Vbz.
One building, two certificates?
posted by Anthea Ng on
E.g. a project has a building which includes Hotel and offices.
2 Pipe Fan Coil System
NC-2009 EAc1:Optimize energy performanceposted by Donald Green on
We have a project where the team came to us after the fact and are asking about LEED certification. They have already installed a 2 pipe fan coil system.
More option D vs option B
NC-2009 EAc5:Measurement and verificationposted by Thomas Huang on
Thank you for this very helpful forum. I have read every comment on EAc5 as I prepare to submit our first M&V plan.
Content of mechanical schedule
NC-2009 PIf4:Schedule and Overview Documentsposted by Michael Haugeneder on
Does the requirement for PIf4: mechanical schedule refer to the provision of MEP plans or simply to HVAC plans?
Constant volume system in some areas, VAV in others
NC-2009 IEQc1:Outdoor air delivery monitoringposted by Muhammad Faisal Azizullah Jaffar on
Hello, my project is a campus golf course community project in Qatar. One of the buildings in the master site, the clubhouse, is mixed-use: part hotel, part retail, part restaurants etc.
Clarification
CS-2009 EAc5.2:Measurement and verification - tenant submeteringposted by Leandro Silva on
Please help with this scenario: Core and Shell project with 8 tenants (light manufacturing). Goal of achieving EAc5.1 and EAc5.2. The developer will meter total energy use of the Core areas and a
LEED Matrix
NC-2009 IEQc8.1:Daylight and views - daylightposted by Oleg Petryuchenko on
we have some spaces that excluded from 8.1 according to matrix such as lobby, brake room.. but they are properly daylit (10-500fc) based on AGI calcs.
Future development in the same LPB
NC-2009 SSc7.1:Heat island effect - nonroofposted by Marcio Alberto Casado Pereira on
Hi folks, In need of some light on a review we received. We have a multiple buldings Project. there are 4 LPBs inside of the LCB.