Question on who can fill the role of a CxA for enhanced commissioning

NC-v4 EAc1:Enhanced commissioning
posted by  A.J. Speicher  on 

Hello.  I had a question about who can fill the role as the CxA for the enhanced credit.  The case is where an engineering firm was hired by the architect to complete the civil/land devel

5
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Sat Mar 7, 2020, 12:50 pm

Leed v4.1 Documentation

LEED v4.1 Discussion Forum
posted by  Stephan Zweig  on 

Hello  LeedUsers,

Is there a link where I could find the documentation for v4.1 version?

Especially for the credits which are new in 4.1, like "Electric vehicles".

2
Senior Sustainability Consultant
Stantec Architecture
LEEDuser Premium Member
20 thumbs up
Sat Mar 7, 2020, 7:06 am

USGBC websites

SD Leaders
posted by  Heather Holdridge  on 

Were we given any warning that LEED Online and USGBC.org would be down for a week?  

33
Director of Sustainability, Senior Associate
FXCollaborative
LEEDuser Premium Member
1 thumbs up
Fri Mar 6, 2020, 5:30 pm

Automatic Receptacles LEED Interpretation

NC-v4.1 EAp2:Minimum Energy Performance
posted by  Sofia Barahona  on 

We are attempting to work on a project in LEEDv4.1, which in Optimize Energy Performance states that ASHRAE 90.1-2016 mandatory provisions must be met.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Mar 6, 2020, 3:59 pm
3
CEO
Green Commons, LLC
LEEDuser Expert
586 thumbs up
Fri Mar 6, 2020, 3:02 am
3
Thu Mar 5, 2020, 8:55 pm

Soldering Paste for Piping Applications

NC-v4 EQc2:Low emitting materials
posted by  Shannon Oletic  on 

Does soldering paste used by the plumbing sub trade need to comply with EQ Low Emitting Material requirements for adhesives and sealants?

Appreciate your insight!

0

v2009 - SSc1: Site Selection - Wetland Protection

NC-2009 SSc1:Site Selection
posted by  Kathy Hrabovsky  on 

Is a Category 1 Forest Conservation Easement permitted to protect the limits of disturbance between a project site and an existing wetland if the project site is 60', instead of 100', from a wetlan

0
1
Thu Mar 12, 2020, 6:30 pm

When to hire a Commissioning Agent

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Peter Davis  on 

We were alerted to this project in Design Development Phase and the next phase has been progressing while we have been hiring and negotiating with the prospective CxA.

3
Artist, Curator, Writer
Teresa Stern Arts
LEEDuser Basic Member
20 thumbs up
Thu Mar 5, 2020, 3:32 am