Log in
Forum » NC-v4.1 LTc8
Topic

Electric Vehicle-required project documentation

NC-v4.1 LTc8: Electric Vehicles
posted by Michelle DeLora on Jan 18, 2022, 12:13 pm

I have a client asking me about Option 2 - which is ESVE ready for 10% of parking. In the online summary of the credit it does not go into the required uploads. I have been bitten in the past on...

Last reply: Mercedes Byers, Feb 14, 2022, 2:21 pm

Signage for EV spaces

NC-v4.1 LTc8: Electric Vehicles
posted by Amanda Polematidis on Dec 6, 2021, 12:34 pm

For those of you who completed the credit, would one sign for an area with EV charging stations suffice, or does each charging station need a sign?

Last reply: Emily Purcell, Dec 6, 2021, 1:08 pm

Option 1: 2% or 5%, Option 2: 6% or 10%?

NC-v4.1 LTc8: Electric Vehicles
posted by Timothy Ian Middleton on Sep 24, 2021, 5:46 am

Thanks to LEED User I just discovered the latest version of NC4.1_LTc8 requires 5% of spaces to comply with Electric Vehicle Charging Requirements, instead of 2%.

My LEED v4.1 Guide (which...

Last reply: emily reese moody, Sep 27, 2021, 2:56 am

Level 1 EV chargers- any credit for extensive installations vs a few Level 2's?

NC-v4.1 LTc8: Electric Vehicles
posted by Pooja Sannamani on Sep 16, 2021, 2:44 pm

Does anyone have any experience in getting credit for more Level 1 chargers?  Increasing having clients question whether Level 2 is the right approach for mass rollout due to electrical...

Last reply: Emily Purcell, Sep 17, 2021, 11:40 am

Existing EV Chargers Serving Project

NC-v4.1 LTc8: Electric Vehicles
posted by Kelli Kimura on Aug 18, 2021, 5:53 pm

Hi all,

Wondering if a project can take credit for existing EV charging stations that are located within the parking spaces used by a project (as long as they meet the EV charger...

Last reply: Nick Semon, Aug 19, 2021, 9:12 am

EV spaces for residential portion?

NC-v4.1 LTc8: Electric Vehicles
posted by MARLOES REININK on Jul 6, 2021, 10:38 am

We have a mixed-use project (office, hotel, & residential apartments). With this credit now specific to EV spaces only, how are the residential occupant spaces addressed? They are assigned...

Last reply: Emily Purcell, Jul 6, 2021, 12:12 pm

EV charging for spillover parking

NC-v4.1 LTc8: Electric Vehicles
posted by Deborah Lucking on May 4, 2021, 2:56 pm

Our project has allocated areas for spillover parking (used a few times a year) in ones and twos around the site, accessible from an alley. much like on-street parking.

We are hoping these...

Last reply: emily reese moody, May 4, 2021, 3:31 pm

EV parking space distribution

NC-v4.1 LTc8: Electric Vehicles
posted by Nadia Bini on Nov 11, 2020, 4:00 pm

Our project has both employee parking and visitor parking. LEEDv4 specified that EV parking needs to be "distributed proportionally among various parking sections (long-term & short-term",...

Last reply: emily reese moody, Nov 11, 2020, 4:49 pm

EV Ready- Raceway

NC-v4.1 LTc8: Electric Vehicles
posted by Jill Kurtz on Nov 3, 2020, 3:13 pm

We have a project that is seeking certification. It shares parking with existing buildings on its campus. The project has capacity for EV parking that would meet the entire campus parking 6%...

Last reply: Emily Purcell, Nov 3, 2020, 4:20 pm

Combination option?

NC-v4.1 LTc8: Electric Vehicles
posted by Joseph Snider on Oct 6, 2020, 3:50 pm

Has anybody seen an option to install some EVs and then some EV ready to combine Option 1 and 2?  In 2009, there was a way to run weighted calcualtions.  We have a project doing a little bit of...

Last reply: Dave Hubka, Oct 21, 2020, 4:03 pm