Number of Bus Routes Required

NC-v4 LTc5:Access to quality transit
posted by  Carolyn Risley  on 

To confirm, is it possible to achieve LTc5 with just one bus route so long as the minimum number of weekday/weekend trips are satisfied?

1
Thu Oct 20, 2016, 4:44 pm

tenant requirements to maintain compliance with IEQc8.1 and 8.2

CS-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Gail Napell  on 

Has anyone had comment from GBCI when taking these credits for a speculative C&S office building? We provide a proposed tenant layout that shows the interior complying with these credits.

1
Thu Oct 20, 2016, 2:25 pm

Supplementary Cementitious Materials

NC-2009 MRc4:Recycled Content
posted by  Shawn Keith  on 

I have my cement tracker all filled out.

1
Wed Jan 18, 2017, 1:43 pm

Option 2. Additional reductions beyond 30%. VS. Reduce LWR 50%

NC-v4 WEc1:Outdoor water use reduction
posted by  Jing Zhang  on 

Outdoor Water Use Reduction Credit Does option 2 means, if reduction ranges from 50% to 100%, then, at least 30% need to be achieved only through plant and irrigation system efficiency.

1
Thu Oct 19, 2023, 1:36 am

want to get information about previous LEED certified projects

NC-2009 PIf2:Project Summary Details
posted by  Amir Salehi  on 

Hello dear professionals, I have got a question and that is it: How can I find detail information about some specific LEED certified projects, I want each project scorecards in detail(for example,

1
Fri Oct 21, 2016, 10:50 pm

detail information about LEED certified projects

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Amir Salehi  on 

Hello dear professionals, I have got a question and that is it: How can I find detail information about some specific LEED certified projects, I want each project scorecards in detail(for example,

1
Sat Jan 7, 2017, 10:55 pm

Visitors for residential units

NC-v4 LTc6:Bicycle facilities
posted by  Sara Johansson  on 

Hello, Where can I find info on regular and peak visitors for residentual units? App 2 does not give any information on residentual units.

1
Mon Nov 28, 2016, 7:55 pm

Transients, visitors and peak visitors

NC-v4 LTc6:Bicycle facilities
posted by  Sara Johansson  on 

The LEED manual states that transients = visitors. The credit requirements are percentages based on peak visitors. Appendix 2 in the manual gives defaults on transients (visitors).

1
Mon Nov 28, 2016, 7:48 pm

Soil Restauration in vegetated roof

NC-v4 SSc2:Site development - protect or restore habitat
posted by  Ana García  on 

Dear All, We are working in a project, in which the whole site was previously developed and paved. All new green areas will be vegetated roofs (project achieves a density of 1.5 floor-area ratio).

1
Tue Jan 17, 2017, 4:41 pm

EPMD Membrane Adhesive

CS-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Anna Bak  on 

In FAQs for IEQc4.2 I found an information that the actual weather barrier does not need to comply with the credit. I understand that we can treat EPMD Membrane as weather barrier.

1
Tue Oct 25, 2016, 1:00 pm