project boundary definition

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Emmanuel Pauwels  on 

Our Project consists of land that is property of the owner.

3
Wed Mar 13, 2013, 1:33 pm

design phase review appeal

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Todd LaFreniere  on 

Our project is currently at the Construction Final Review Stage and we would like to submit an appeal on 2 of our Design credits. How is this done?

5
Wed Mar 13, 2013, 2:30 am

Failed LEED ND Stage 1 Prerequisite

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Bernard Sagaiyaraj  on 

I have received my LEED ND Stage 1 review results which contained 2 failed prerequisites. Can I proceed to Stage 2 and correct them there?

7
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Wed Mar 13, 2013, 2:00 am

Which Parking Areas to Include?

NC-2009 PIf2:Project Summary Details
posted by  Kevin Flynn  on 

I am beginning work on a fairly complex project. The portion of the project seeking LEED certification is an office building attached to an existing building.

2
Wed Mar 13, 2013, 1:39 am

CS and CI fee relationship

NC-2009 PIf2:Project Summary Details
posted by  Melissa Merryweather  on 

I have a project where we are doing a CS certification for the building owner and a CI project for the main tenant at the same time. I was about to submit both for Preliminary Certification.

3
Wed Mar 13, 2013, 1:14 am

Certifying one LEED building on a campus

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Lisa Sawin  on 

We have currently drawn our LEED boundary to include all areas that our building/scope of work is impacting.

2
Wed Mar 13, 2013, 12:09 am

Data Centers - Efficiency for UPS and computer servers for the

NC-2009 EAp2:Minimum energy performance
posted by  Carlos Garcia  on 

Dear all We're working in the energetic simulation for the credit EA p 2 in LEED NC 2009 in a Data Center building.

5
Tue Mar 12, 2013, 10:08 pm
3
Sustainability Professional
LEEDuser Expert
430 thumbs up
Tue Mar 12, 2013, 6:51 pm

Natural Ventilation: Which spaces are to be considered?

NC-2009 IEQp1:Minimum indoor air quality performance
posted by  Marco Abdallah  on 

1. Are only regularly occupied spaces to be considered or all generally spaces (including stairs, corridors, storage and technical rooms)? 2.

4
Default Avatar
HVAC consultant
Optimized Systems
LEEDuser Basic Member
19 thumbs up
Tue Mar 12, 2013, 5:08 pm

Thermal Comfort (IEQc 7.1) for Industrial Applications

NC-2009 IEQc7.1:Thermal comfort - design
posted by  Ismaiel Salama  on 

We are targeting this credit for a project with more than 70% of the buildings are utilised for industrial, processing, storage and manufacturing activities.

4