General Emission Evaluation and VOC Content for signage

CI-v4 EQc2:Low emitting materials
posted by  Gabriela Mena   on 

We are documenting a LEED/WELL project and we want to know if we must include the certification for the signage (branding, emergency exit, etc.) because we do not know in which category it should b

1
Mon May 21, 2018, 7:30 pm

Retro-commission an existing PV array?

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Deborah Lucking  on 

Our project is a county-owned building which will utilize renewable energy from an existing, adjacent, county-owned PV farm.

1
Wed May 16, 2018, 1:05 pm

outdoor air quality mesurements

CS-2009 IDc1:Innovation in Design
posted by  Agnieszka Rylska  on 

One of our clients is planning to install an outdoor air quality station on his building.

1
Thu May 17, 2018, 12:59 am

Multiple CxAs?

NC-v4 EAc1:Enhanced commissioning
posted by  LUCY WILLIAMS  on 

Have any project teams had success using two different commissioning agents from two different entities in order to perform commissioning services on their project?  For example, can the

1
Tue May 15, 2018, 2:19 pm

Diverted vs Commingled in LEED Online Form

NC-2009 MRc2:Construction Waste Management
posted by  Dionisio Franca  on 

Hello!

The LEED Online Form has three option under Disposal Method: Commingled, Diverted, Landfill Waste. By choosing "commingled", you can input the percentage diverted. 

4
Default Avatar
LEEDuser Expert
472 thumbs up
Tue May 15, 2018, 4:59 am

Treatment Requirements

NC-v4 SSc4:Rainwater management
posted by  Annie Levan  on 

Hello,

Can someone please clarify the treatment requirements for various storm water strategies? A few example strategies are as followed:

0

Building eyebrows count towards area?

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  Nicole Kimoto  on 

We have a project where we have concrete eyebrows protruding from the building exterior. Would the area of those eyebrows count towards roof area?

9
Building Enclosure Consultant
BPL Enclosure
LEEDuser Basic Member
58 thumbs up
Mon May 14, 2018, 9:40 pm

Percent of Occupants

NC-v4 WEp2:Indoor water use reduction
posted by  Amy Ruffino  on 

On the Reduction Calculation spreadsheet, how should the "Percent of Occupants" be filled out for kitchen sinks or urinals?

11
Architect - Cx Provider - Building Performance Specialist
GLHN Architects & Engineers
LEEDuser Premium Member
25 thumbs up
Mon May 14, 2018, 9:17 pm

And/or Options?

EBOM-v4 SSc1:Site Development- protect or restore habitat
posted by  Branka Zivkovic  on 

Hello,

Reference Guide says in Requirements that that it is Option 1 (On-site restoration) OR Option 2 (Financial support).

2
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Mon May 14, 2018, 8:32 pm

ZNE Plug loads

Green Commons
posted by  Meredith Elbaum  on 

 

Hi All,

1
Mon May 14, 2018, 6:56 pm