Defining number of parking spaces
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Lisa Sawin on
We have a new office building that is on an Existing VA campus. There are no other LEED projects to date on the campus.
Insufficient Cooling Capacity
NC-2009 EAp2:Minimum Energy Performanceposted by Yoyo Shek on
Dear All, According to 90.1, the HVAC system shall follow the design for proposed case. I wonder what if the HVAC engineer under-sizes the cooling capacity.
MRc5 question:
EBOM-2009 MRp1:Sustainable Purchasing Policyposted by Heather Holdridge on
Does MRc5 count as an alternative to MRc2-4 or not? It seems like it does, however in the MRp1 policy document template it says it doesn't. Could someone please clarify? Thanks!
use of LEED logo
posted by Tristan Roberts on
Antonio, I'm surprised USGBC sent you here, as it seems like they would have more expertise on use of their own logo. I would refer to their policy as you suggested.
Signatory
NC-2009 IEQp2:Environmental Tobacco Smoke (ETS) Controlposted by Kris Phillips on
My understanding is that the Owner must place her/his initials in the Signatory box for credits such as this one (No Smoking).
NAUF & CARB 2
NC-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Productsposted by John Casciato on
If a product meets CARB or CARB 2 compliance, does it meet this credits needs?
Commingled Recycling Problem
EBOM-2009 MRc7:Solid Waste Management—Ongoing Consumablesposted by Ryan Gardner on
The project im working on has a "unicycling" bin in which both garbage and recyclables all go into one dumpster to be sorted off site.
Does reconstituted veneer have to comply with IEQc4.4?
NC-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Productsposted by Jason Grant on
Reconstituted veneer is basically layers of wood that are glued together and then sliced into veneer which is subsequently laminated to various core materials to make veneer panels.
adding credits to review in DEsign Review
posted by Inés Alomar on
We have submitted a few number of credits on the Design Review from the whole credits related to the Design Phase, because the property wanted us to start and some aspects couldn't be solved on tim