Supplemental Calculator

Schools-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Lauren Fakhoury  on 

This supplemental calculator Excel file only seems to create problems every time I used it!

4
Tue Nov 22, 2011, 8:59 pm

Which rating system to choose?

LEED for Healthcare forum
posted by  Francesco Allaix  on 

Nice that you have opened this forum Tristan. I have a few questions concerning LEED HC. We have a project where 100% of the space is healthcare facility.

3
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Nov 22, 2011, 8:53 pm

Project Boundary, Site Boundary and Building

CI-2009 SSc1:Site Selection
posted by  Arlee Fisher  on 

We are working on a remodel project encompassing three distinct areas within one portion of a hospital and I am not confident with my understanding of the definitions of Project Boundary vs.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Nov 22, 2011, 4:28 pm

Hospital Fixture Groups

NC-2009 WEc3:Water Use Reduction
posted by  Susan Walter  on 

I'm debating how to set up my fixture groups for a large healthcare project. Initially, it makes sense to split into two groups: inpatient and outpatient/other.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Nov 22, 2011, 1:43 pm

Lavatory Faucet default duration change during construcion.

NC-2009 WEc3:Water Use Reduction
posted by  BH .  on 

Hi, Due to "Water use reduction Additional Guidance" from July 14,2011 Nonresidential Default Lvatory Faucet duration has changed from 15 to 30 sec.

2
Mechanical Engineer
Integral Group
LEEDuser Expert
342 thumbs up
Tue Nov 22, 2011, 8:28 am

new project with old HVAC

NC-2009 EAp3:Fundamental Refrigerant Management
posted by  Timo Marquez  on 

I would like to know if the following complies with EAp3: We have a new construction (in process 2011) and the owner is purchasing an old HVAC systems that used R-12.

2
Default Avatar
Dir. Innovation
Green Soluce
LEEDuser Basic Member
13 thumbs up
Tue Nov 22, 2011, 5:02 am

Fenced playgrounds

Schools-2009 SSc5.2:Site Development—Maximize Open Space
posted by  Daniel McDonald  on 

We are working on an urban school renovation (SSc2=yes), and I am wondering if having the playgrounds and other outdoor areas behind fences affects this credit at all - are they still "pedestrian o

3
Mon Nov 21, 2011, 9:15 pm

LEED project defined boundary 1.5 buildings

CI-2009 EAc3:Measurement and Verification
posted by  Steve Khouw  on 

Just to be sure, to be sure, not trying to be picky here. Our new LEED-CI project encompasses 2 buildings, but only 1 is going to be fully occupied and the other only partially,

3
Principal
DNA GreenDesign
LEEDuser Basic Member
126 thumbs up
Mon Nov 21, 2011, 8:55 pm
5
Architect, Sustainability Lead
LEEDuser Basic Member
8 thumbs up
Mon Nov 21, 2011, 8:37 pm
4
Default Avatar
Sustainability Consultant
UHG Consulting
LEEDuser Basic Member
10 thumbs up
Mon Nov 21, 2011, 6:12 pm