LPD for IT Rooms and IT ClosetCI-v4 EAp2: Minimum Energy Performanceposted by Edgar Arevalo on Oct 5, 2023, 3:36 pm
So according to 2010 ASHRAE 90.1, there is no... Last reply: Marcus Sheffer, Oct 8, 2023, 11:03 am |
|
AEDG for LibrariesCI-v4 EAp2: Minimum Energy Performanceposted by Edgar Arevalo on Aug 14, 2023, 10:45 am
I have a CI project for a Library. The team is looking to pursue prescriptive compliance for this credit. The issue is when attempting to complete the AEDG table, I don't know which category... Last reply: Marcus Sheffer, Sep 29, 2023, 3:19 pm |
|
Baseline Lab System for fit outCI-v4 EAp2: Minimum Energy Performanceposted by Cory Duggin on Mar 20, 2023, 12:11 pm
I am working on a CI project that is the fit out of two floors of an existing lab building. The only HVAC available to the fit out floors is 100% OA from the DOAS units and warm chilled water... Last reply: Cory Duggin, Sep 29, 2023, 10:30 am |
|
Baseline Building HVAC systemsCI-v4 EAp2: Minimum Energy Performanceposted by Paula Hernandez on Sep 4, 2023, 1:08 pm
Hi, We are modeling a portion of a building. The building counts with two dedicated outdoor air systems that provdie outdoor air to the whole building. We know the amount of... Last reply: Tyler Thumma, Sep 29, 2023, 9:13 am |
|
Minimum Energy PerformanceCI-v4 EAp2: Minimum Energy Performanceposted by Nagaraj Sankar on Aug 22, 2023, 8:09 am
As we have a VRF system for fresh air, we design a seperate proposed case system module for the fresh air system. Is base case system is required in this scenario should also be taken into... Last reply: Marcus Sheffer, Aug 22, 2023, 10:57 am |
|
Option 2. Prescriptive ComplianceCI-v4 EAp2: Minimum Energy Performanceposted by Dave Hubka on Oct 15, 2021, 10:45 am
kinda embarrassed to ask this one, but here goes... The ref guide and credit template require the team to upload the Target Finder performance results when pursuing Option 2. Prescriptive... Last reply: Michelle Rosenberger, Aug 15, 2023, 11:51 am |
|
Modeling baseline building envelope for CI project, Purchased energy (condenser water)CI-v4 EAp2: Minimum Energy Performanceposted by Yousef Abougabal on Mar 27, 2023, 1:50 pm
Project Type: LEED ID+C (CI) Version 4 Energy & Atmosphere, EAp2: Minimum Energy Performance & EA Credit: Optimize Energy Performance Option 1 - Tenant Level Energy... |
|
TI Office Building Modeling Approach for Areas Outside of the LEED ScopeCI-v4 EAp2: Minimum Energy Performanceposted by elvin ruya on Mar 21, 2023, 11:50 am
Hi, The LEED scope of the TI project I have includes some spaces in 1st floor, whole 2nd, 16th and 17th floors. Is it required to model the whole building area even though it is outside of... Last reply: Marcus Sheffer, Mar 21, 2023, 3:06 pm |
|
Model the Additional Lighting allowances for baseline and proposed casesCI-v4 EAp2: Minimum Energy Performanceposted by Michael on Feb 7, 2023, 4:41 am
My jewelry store (100m2) has general lighting on the ceiling and millwork lighting for decorative purposes. The general lighting is 16W/m2 compared to the baseline of 18 W/m2. The millwork... Last reply: Marcus Sheffer, Feb 7, 2023, 12:21 pm |
|
LEED Modeling Requirements for a CI projectsCI-v4 EAp2: Minimum Energy Performanceposted by elvin ruya on Nov 9, 2022, 3:32 pm
Hi, Last reply: Marcus Sheffer, Nov 9, 2022, 4:46 pm |