Forum quick links
Pilot Credit #44 Ergonomics Strategy - LEED User registration
Pilot-Credits EQpc44:Ergonomics approach for computer usersposted by Cindy Davis on
I received a comment back from our LEED preliminary design review that the 'reviewer' is unclear if the project team representative (me) has registered with LEEDuser, since a completed survey has n
Sub-metering in Option D
NC-2009 EAc5:Measurement and Verificationposted by Alicia Villanueva on
Marcus Sheffer posted some months ago in this credit: "You will need to calibrate the model by energy end use on a monthly (and annual) basis. [...] Yes you would need to separate out the electric
MPR#6 - Option 1: Sharing data via Energy Star Portfolio Manager
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ron Dean on
One of the projects I'm working on in Peru, is persuing the option 1 of MPR#6 (through Energy Star Portfolio Manager:ESPM) so we can get one EP point in EAc5.1. So, my questions are: 1.
No new parking, can we still achieve Option 1?
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Eamon Geary on
The project I am working on is a new facility on a pre-existing campus. There are is no new parking added and all new employees are expected to find parking spots on their own.
Biomass from energetic crops
CS-2009 EAc2:On-site Renewable Energyposted by BH . on
Hi, does LEED recognize the biomass from energetic crops such like: -short rotation coppice (Poplar and willow include) -Grasses and non-woody energy crops (Miscanthus and Hemps included) Tha
Consistency in regularly occupied and unconditioned areas
NC-2009 PIf3:Occupant and Usage Dataposted by Alicia Villanueva on
My project team is aware that the total gross area must be consistent through PIf3 and EAp2 forms. We wonder whether or not it is also required to have consistency in "regularly occupied" and "unc
Itemized Structural Steel Calculation
NC-2009 MRc4:Recycled Contentposted by Erik Heck on
We have a supplier's documentation spreadsheet for structural steel listing each separate material (HSSs, beams, channels) with weight, cost, post and pre-consumer percentages.
Contractor reuse of waste materials on their other projects
NC-2009 MRc2:Construction Waste Managementposted by John Covello on
Hello, Our contractor will most likely reuse some waste materials on their other projects if they have any left over.
FSC certified subcontractor?
NC-2009 MRc7:Certified Woodposted by Erin Holdenried on
Does a subcontractor, who is cutting and finishing FSC wood in their own facility and installing it in the project have to be FSC certified?