EBOM-2009 EAp2:Minimum Energy Efficiency Performanceposted by Charalampos Giannikopoulos on
LEED Online requests a copy of the complete Statement of Energy Performance (SEP).When generating the statement, it is noted to make sure to select the following report options: Statement of Energy
Roof/Terrace
NC-2009 SSc7.2:Heat Island Effect—Roofposted by Lauren Bellamy on
The project I am working on has a canopy over a terrace, and below the terrace is conditioned space.
District graywater recycling system
NC-2009 WEc3:Water Use Reductionposted by Brian Meinrath on
I am working on a large project that includes over 10 buildings.
High Pressure Sodium lamps--interior or exterior?
Healthcare-v2009 MRp2:PBT source reduction - mercuryposted by Maria Unruh on
The table MRp2-2, is this for HPS lamps for the entire project or for the interior only?
Natural Ventilation on HAP
NC-2009 EAp2:Minimum Energy Performanceposted by Khaled Fouda on
Hey All, This question is basically for the energy modelers out there who use HAP or any other software. I have a conditioned lobby where the fan coil just uses the return air, according to our ca
Injected foam insulation with 0 g/L VOCs
Schools-2009 IEQc4.6:Low-Emitting Materials—Ceiling and Wall Systemsposted by Erin Holdenried on
I have a project using Injected foam insulation with 0 g/L VOCs. Does this product meet the credit intent? Or must it meet the specific CDHS testing requirements?
Multiple Building or One Building?
CS-2009 MPR2:Must be a complete, permanent building or spaceposted by Muge Karasahin on
We have a large scale international project, consists of five attached building blocks (A-B-B1-B2-C) that share 7 basement and 7 ground up floors but each have different amount of total floor level
Historical Landmark
CS-2009 EAp2:Minimum Energy Performanceposted by Muge Karasahin on
We have a large scale international project in the eastern Europe.
LEED EBOM EA c.4
EBOM-2009 EAc4:On-Site and Off-Site Renewable Energyposted by Fabio Frescia on
Hello, I have a LEED EBOM project in Thailand. I am now dealing with EA c.4 - On site or Off site Renewable Energy.
ASHRAE 55 - apartment
NC-2009 IEQc7.1:Thermal Comfort—Designposted by Indochine Engineering VN on
My project has apartments and penthouses on the top. Engineers design VRF with thermostat and residents can control their comfort thermally.