Golf Course Clubhouse Project Advice
EBOM-2009 EAc1:Optimize Energy Performanceposted by Johanna Hendricks on
Hello, We have a client that has approached us about the possibility of certifying a golf course clubhouse via LEED EBOM.
Limited LEED CI boundary
CI-2009 MPR2:Must be a complete, permanent building or spaceposted by Kevin Wilcox on
We have a project where the scope of interior alteration is limited to multiple core restrooms (multiple floors) to incorporate ultra low flow fixtures, minor remodel for compliance with building c
Occupied Roof Areas
NC-2009 SSc7.2:Heat Island Effect—Roofposted by Victoria Civitillo on
Can the areas on the roof that are being used for recreations purposes: restaurant, poolside, lounge, etc. be exempt from the roof square footage calculation?
Pilot credit # 45
Pilot-Credits SSpc45:Site assessmentposted by Devani PERERA on
I do agree with Loic that in France, projects that pursue the french certification HQE would perform a site analysis to assess the needs, opportunities and issues that need the most attention.
Solar Panels
NC-2009 SSc7.2:Heat Island Effect—Roofposted by Amanda Johnson on
Hello, We have a project with Thermal solar panels for hotwater, and I just want to double-check that they can be deducted from the roof-surface for this credit since most of the documents (and pos
0% credit achievement rate?
CS-2009 EAc5.2:Measurement and Verification—Tenant Submeteringposted by Graham Langton on
I'm seeing the credit achievement rate as 0% for this credit. Other achievement rates seem OK. Has nobody achieved this credit? Can this be verified?
Multi-purpose unit for 4-pipe systems
NC-2009 EAp2:Minimum Energy Performanceposted by Francesco Passerini on
I'm considering a "Multi-purpose indoor unit for use in 4-pipe systems for the simultaneous production of chilled and hot water by means of two independent water circuits".
Recycled cork can contribute to achieve MRc6?
NC-2009 MRc6:Rapidly Renewable Materialsposted by Ricardo Sá on
We're working in a project that use a thermal coating based on cork material. This cork is 100% recycled. Can this material contribute to achieve both credits (MRc4 +MRc6)?
Confusion over tile
Schools-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Crista Shopis on
Above in the "Birds Eye View" tab, it says "Resilient flooring, rubber flooring, ceramic tile, and prefinished wood flooring all must be FloorScore or Greenguard Children and Schools certified." Bu
How many people per control
CI-2009 IEQc6.2:Controllability of Systems—Thermal Comfortposted by Matthew Catterall on
In the checklist above under 'How many people per control?' it states that a single mechanical system control can serve up to two occupants... So, if one thermostat is provided in a room that thre