Can anyone share approach taken to comply with this or related Certified Multi-attribute Products and Materials?
Pilot-Credits MRpc103:Integrative Analysis of Building Materialsposted by Panu Pasanen on
Hi, this looks pretty demanding spec, as the related "Certified Multi-attribute Products and Materials".
Pilot credit - Building Material Human Hazard & Exposure Assessment
Retail-CI-v4 INc1:Innovationposted by Stacey Olson on
It appears that using 5 products which have Declare Labels and/or which are listed on the Pharos site would satisfy the requirements of this credit. Can you please confirm.
Thanks,
Preliminary and Final Design Review Submission - Online Steps for Final Design Review
posted by Stephen Sgro on
We received our preliminary design review report. All credits that were pending and ones requiring revisions have been revised and additional documents have been uploaded.
CALGreen certification as alternate to Watersense?
CI-v4 WEp1:Indoor water use reductionposted by Paladino "Team" on
Would GBCI accept a plumbing fixture that is CALGreen certified as an alternative compliance path to the Watersense requirement?
Concerns with FRP cladding
posted by Vikram Sami on
We are looking into different building skin materials from including GFRC and FRP (amongst others) as alternatives to precast.
Establishment period for 50% landscape water use reduction
NC-2009 WEc1:Water Efficient Landscapingposted by Dimuth Kurukulaarachchi on
All mention of establishment periods refer to the no potable water/irrigation case (WEc1 Option 2), but what about for Option 1, 50% non-potable water use reduction?
Temperatures for Tab.6.8.1I
CS-v4 EAp2:Minimum energy performanceposted by Francesco Passerini on
According to Tab.6.8.1I for test procedure for VRF systems we have to consider AHRI 1230. I’m considering AHRI 1230 version “Approved by ANSI on 2 August 2010”.
Accessible Floor and Ceiling system
CI-v4 MRc2:Interiors life-cycle impact reductionposted by roma goyal on
Hello,
I would like to know what does "accesible floor and ceiling system" mean?
Does it mean suspended ceiling system and raised floor system for 50% of the total floor area.
MLO Non-Residential Lighting using the Performance Method
NC-v4 SSc6:Light pollution reductionposted by Candace Cohen on
The MLO says that in order to establish the Total Initial Site Lumens one must use Table D, adding together the Allowed Lumens Per Square Foot and the Allowed Base Lumens Per Site.
LEED ID+C: TIME, BOUNDARY AND OWNER
posted by ARDOR GREEN on
Dear all,
A building with 8 rooms that have similar areas of 3,825 sqm is under construction phase. Its owner wants to get LEED ID+C certification for R&D room.