Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Furniture included?

NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  severine secret  on 

Using LEED NC 2009, do we need to include furniture items, such as workstations, task chairs and their related components as required for IEQ.45 in LEED CI requirements?

1
Tue Jul 17, 2012, 5:02 pm

Two Year HVAC Electricity Use

CI-2009 EAc4:Green Power
posted by  Joseph Greene  on 

Our LEED project occupies 30% of the total building floor area. The energy model modeled the entire building due to a central boiler and condenser water plant.

1
Fri Aug 31, 2012, 2:10 pm

sanitary installations within tenant fit-out

NC-2009 WEp1:Water Use Reduction—20% Reduction
posted by  Michael Haugeneder  on 

Hello all, Our current core&shell project does not include sanitary installations, which will only be built at tenant fit-out stage.

1
Fri Jul 27, 2012, 9:24 am

certification boundary

General forums
posted by  Michael Haugeneder  on 

Hello, I would like to ask some questions about the certification boundary. 1. A project of mixed use (retail+offices and hotel) is being certificated within 5 floors.

1
Thu Oct 4, 2012, 4:31 pm

natural ventilation in underground parking?

CS-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Michael Haugeneder  on 

Hello, is it possible to aim the credit IEQc5 if a project doesn't have a mechanical ventilation in the underground parking (UP)?

1
Sat Sep 1, 2012, 7:49 pm

single stream recycling

CI-2009 MRp1:Storage and Collection of Recyclables
posted by  Adam Targowski  on 

Will the requirements of this prerequisite be complied with only by having a waste storage room for the whole building with one container for a single stream recycling (that will accommodate all fi

1
Wed Jul 18, 2012, 4:30 pm

no change of flow fixtures

CI-2009 WEp1:Water Use Reduction—20% Reduction
posted by  Adam Targowski  on 

We have a project that consists of an office space with toilets however the folw fixtures are not going to be changed. Is this project exempt from earning this prerequisite?

1
Fri Aug 31, 2012, 12:03 am

Wooden fire door - security requirement

CS-2009 MRc6:Certified Wood
posted by  Jose Antonio Kovacevic  on 

We are certifying a Core and Shell office building.

1
Fri Aug 31, 2012, 3:05 pm

Minimum drawdown rate calculation

EBOM-2009 SSc6:Stormwater Quantity Control
posted by  Meryl Corsun  on 

I am trying to verify that the cisterns on site release stormwater quickly enough to capture 2-year 24-hour design storm events by calculating the minimum drawdown rate.

1
Fri Nov 23, 2012, 9:11 pm

Location of the sign "You are entering a no smoking area"

NC-2009 IEQp2:Environmental Tobacco Smoke (ETS) Control
posted by  Gail Shepherd  on 

We are using option 2 - prohibit on-property smoking within 25 feet of entries....The owner has asked if they can locate these signs on the building door.

1
Fri Jul 27, 2012, 7:32 pm