CS-2009 EAp2:Minimum Energy Performanceposted by Anna Korinkova on
Dear fellow LEEDusers. Our base building (C&S) has not included a service hot-water system (it will be installed by tenants later) and therefore we modelled the Proposed Building Performance an
Land Trust Approach - Donation of $ vs Donation of Land
NC-2009 SSc5.1:Site Development—Protect or Restore Habitatposted by Abena Darden on
Hell all - I've been trying to understand the requirements of the SS 5.1 ACP which allows donation of offsite land in trust.
U Value & SHGC
NC-2009 EAp2:Minimum Energy Performanceposted by SSN Energy Model on
Hi, We are in the process of doing Energy Simulation for Garments Factory. We have completed the base case part and proposed case is pending.
minimum air flowrates in Baseline Case
NC-2009 EAp2:Minimum Energy Performanceposted by Charline SEYTIER on
Hi, We are in the process of responding to the comments we received from the reviewers on the energy model of one of our project performed with eQuest. The reviewer is asking us to provide an inpu
Calculation Issue
NC-2009 SSc2:Development Density and Community Connectivityposted by Farah A. on
A building pursuing the Development Density and Community Connectivity credit is located within a 2 acres community (8,093,m²), in which existing buildings total 90,000 sq. ft (8,361 m²).
HVAC baseline system
NC-2009 EAp2:Minimum Energy Performanceposted by Gabriela Crespo on
Dear all, I have a question regarding an HVAC baseline model for systems 7 and 8. We have a project located in a very arid zone, where water is very limited.
System manages the 1:5 and 1:100 year event - compliant?
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Lindsey Kindrat on
In my region, the DP requires that the major storm system be designed to convey runoff from the 1:100yr event (and minor system to convey the 1:5yr event).
Multiple forms reqt. for AGMBC approach-LEED EBOM 2009 WEp1, C1
EBOM-2009 WEp1:Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by Kevin Sullivan on
Hi We are using the group approach under AGMBC ( Application Guide for Multiple Buildings and On-Campus Building Projects) guide for six buildings under the project's scope.